Problems, changes delay Utah project end until March

The reconstruction project on Utah Street will not be completed until the middle of March because of problems encountered during construction and changes to the project.

The $1.8 million project includes creating trenches for electrical conduits as well as installing a transformer pad, vaults, junction boxes, street lights, new water services and fire hydrants.

“The biggest reason for the delays was the underground electrical conduits, both for the city’s system and for the streetlights,” said Boulder City Public Works Director Scott Hansen. “The contractor encountered hard material which slowed down daily trenching production.”

Another element of the project’s new timeline is the coordination between the city and the Regional Transportation Commission of Southern Nevada.

“In the Las Vegas Valley, the utility companies and the roadway agencies try to work together to coordinate projects, but you occasionally see a new road ripped up just a few years after it is complete for a utility project,” he said. “Here in Boulder City, the coordination is awesome, since the city has all of the major utilities. Instead of several costly projects over a few years, the city bundles utility projects with roadway projects. This is more efficient for the ratepayers and the taxpayers, but projects end up being longer. But once the project is complete, hopefully the city does not have to do construction on this road for 30 years.”

The city and RTC are sharing the cost of the project.

Contact reporter Celia Shortt Goodyear at cgoodyear@bouldercityreview.com or at 702-586-9401. Follow her on Twitter @csgoodyear.

MOST READ
LISTEN TO THE TOP FIVE HERE
THE LATEST
Search for Central Market tenant continues

It’s been just short of two months since of a trio of friends, who are also longtime local property and business owners, made an announcement that piqued the interest of many in Boulder City.

About 83% of students feel safe at BC schools

Councilwoman Sherri Jorgensen was full of praise regarding a recent all-schools event at the high school.

Local aid groups get fed grant funding

The city has approved disbursement of almost $255,000 in federally-supplied community development block grant (CDBG) funds to three local entities: the Senior Center, Emergency Aid and Lend A Hand.

Planning commission approves Tract 350 variance request

Toll Brothers bettered their record in front of the planning commission to 2-1 last month when the developer got approval for a variance request related to the width of lots in Tract 350.

Kicking Off the New Year

Boulder City High School held its traditional back-to-school assembly this past Friday. School spirit and enthusiasm filled the gym as classes competed against one another to hold the coveted Spirit Stick. Aside from games, members of the fall sports teams performed to songs.

BC Electric’s Medo makes accusations about e-bike/scooter law

While the great majority of public comment surrounding the issues of unsafe usage — often by juveniles — of e-bikes and electric scooters was firmly on the side of the city “doing something,” not everyone is onboard.

So where does that RDA money come from?

It wasn’t all about donuts or whether super bright pink is an appropriate color for a building in the historic district. In addition to donuts it was about, well, dollars.

King to participate in essay contest

Last week, it was announced that fourth graders throughout the state are invited to participate in an essay contest, with the winner receiving the honor of lighting the 2025 U.S. Capitol Christmas Tree in Washington, D.C.

Really better buy that helmet

With a couple of significant amendments, the city council voted unanimously to pass an ordinance regulating the use of e-bikes and e-scooters in Boulder City. The ordinance passed unanimously Tuesday and will take effect on Sept. 18.