Bypass construction on schedule; set for 2018 completion

Construction of the Interstate 11 bypass is progressing as planned, with part of it coming along faster than expected, according to the Nevada Department of Transportation.

NDOT Public Affairs Officer Tony Illia said Phase 1, it’s portion of the interstate project, is 37 percent complete and is ahead of schedule.

“We are actually moving much faster than expected,” Illia said. “We are expecting to be done with our part of the project by December 2017.”

Phase 1 is a $82 million project that involves building a 2.5-mile, four-lane concrete interstate freeway between Silver Line Road and Foothills Drive.

Construction crews have currently moved 1 million cubic yards of earth in the Phase 1 area.

Illia said the amount of dirt moved to construct the bypass is enough to fill 400 swimming pools.

A full diamond interchange also will be constructed near Railroad Pass hotel and casino. The interchange will allow constant four-way traffic by implementing a series of ramps and overpasses.

U.S. Highway 93/95, where the casino is located, sees a high amount of traffic, with over 35,000 vehicles and heavy trucks driving through the area daily.

“We get a lot of traffic near Railroad Pass,” Illia said, “The interchange will keep the heavy traffic flow moving.” Phase 2 is managed by the Regional Transportation Commission of Southern Nevada is also on schedule to complete the other 12.5 miles of the interstate by 2018. Phase 2 is being worked on concurrently with Phase 1. “We started construction in 2015 and we are currently on schedule to finish in 2018,” RTC representative Monika Bertaki said. “Bridge construction, drainage structures, utility work, dust control, fencing and earthwork removal should be completed on time.”

Bertaki said bypass construction will cause minimal community disruption because it is being built away from U.S. Highway 93/95.

For more bypass updates, head to NDOT’s or the RTC’s web page at http://bit.ly/1NWorKT or http://bit.ly/19oj6It.

Contact reporter Max Lancaster@bouldercityreview.com or at 702-586-9401. Follow him on Twitter @MLancasterBCR.

MOST READ
LISTEN TO THE TOP FIVE HERE
THE LATEST
City to appeal BLM’s data center plan

In a unanimous vote, the Boulder City Council voted to appeal the Trump administration’s unpopular approval of a data center that shut the public out.

Search continues for store tenant

It’s been a year since a trio of local business owners and friends purchased the former Central Market with a plan of bringing a second grocery store to Boulder City.

Chris Render takes over varsity football program

Ready to set the tone with a new culture and identity, the Boulder City High School football program will be helmed by Chris Render this upcoming season.

Data center petition falls short

A recent petition seeking to add three questions to this year’s general election ballot, one of which deals with data centers, failed to receive enough verified signatures in order to move forward.

City reaches agreement with Blue Collar employees

Late last month, the Boulder City Council approved a new three-year Collective Bargaining Agreement (CBA) for the Teamsters Local 14 Blue Collar Bargaining Unit (BCBU).

Data center proposal withdrawn

The developer who proposed a data center near I-11 and US-95 has withdrawn its application to the Boulder City Land Management Process.