Price for pool project up sharply

Since inflation started to really take off in early 2022, the cost of everything seems to have gone up: eggs, gasoline, rent. And it appears that proposed construction projects are not immune from the effects of rapidly-rising prices.

In their Aug. 8 meeting, the Boulder City Council got a presentation updating estimated costs for a proposed new facility to replace the city’s aging pool. When the council received the initial estimate from SCA Design in 2021, the cost of replacing the entire facility was tagged at more than $27 million. At the end of February of this year, after receiving an update on conceptual plans and potential costs, the council directed city staff to seek an update to the original cost estimate accounting for what was assumed would be higher costs.

That updated estimate came last week and the price tag has increased to more than $36.7 million, a 36% increase over the 2021 estimate.

A representative of SCA Design gave a presentation at which she outlined the parameters of the proposed project that had been presented to the Municipal Pool Ad Hoc Committee which recommended that the city move forward with the project. “Given the state of the world economy, the United States economy and specifically here in Boulder City, you’re going to see quite a bit of a cost difference,” she said before presenting the numbers.

The current municipal pool facility dates from the early 1980s and is in need of repair or replacement, that much is undisputed (outside of one voice during public comment who called for the razing of the existing pool without replacing it). And council members who spoke were supportive of building a new facility. The conflict comes when considering how to pay for it and that process was complicated by the greatly increased cost estimate.

The most obvious route for most city governments would be to issue a bond to finance the pool with the costs being payed over a longer term. But Boulder City is not like other municipalities in that it operates almost totally on a cash basis. The only outstanding debt the city is currently on the hook for is a bond that was used to pay for a water line and even that is paid in advance of what is actually owed.

The plan last year was to use the proceeds from the sale of a tract of land bordering Boulder Creek Golf Club known as Tract 350 to fund the project. Negotiations with the luxury residential home developer Toll Brothers fell through when they were not able to agree to terms.

Both city staff and Toll Brothers reported in February that interest in consummating a transaction was still there. In a story published in the Boulder City Review, Robyn Hogan, Toll Brothers vice president of land acquisition said, “We remain interested in the parcel.”

City Manager Taylour Tedder reported that the city was still interested as well.

“The housing market has changed since the conversation started with Toll Brothers,” he said in the same Feb. 28 news story. “Property on golf courses is still very desirable, especially due to the fact golf courses can no longer be constructed in Southern Nevada.”

While water may seem more plentiful with regular reports of Lake Mead being at higher levels than 2022 coming every week in 2023, there is still a water crisis all along the Colorado River and in 2021, the Southern Nevada Water Authority mandated that golf courses constructed after that point could not use Colorado River water for irrigation which, given that 90% of water used in the Las Vegas Valley and Boulder City comes from the Colorado River resulted in a de facto ban on new courses.

“Toll Brothers will hopefully have information for us in the spring regarding the property. I believe we can find a way to move forward that benefits Boulder City residents and the new aquatic center in the near future,” Tedder said in February.

But spring passed and as residents begin to look toward late summer, there has been no news about renewed negotiations. But Tedder remains optimistic. “I expect this item will be revisited at a council meeting to discuss options in the next couple of months,” he said in an email message last week.

MOST READ
LISTEN TO THE TOP FIVE HERE
THE LATEST
Spring Jamboree features something for everyone

If one is looking for an event that checks just about every box to have a fun weekend in Boulder City, the annual Spring Jamboree is just that.

Track teams shine at home meet as girls dominate

Continuing to excel in weekday events, both Boulder City High School track and field programs shined on their home turf.

Private helipad is becoming closer to reality

A request to build a private residential heliport cleared a second hurdle last week during more than an hour-long presentation and discussion.

Longtime resident turning 100

The number of Americans who are 100 years or older is expected to hit 101,000 this year.

Baseball knocks off 5A foe Coronado

Playing inspiring baseball, Boulder City High School knocked off 5A Coronado 10-8 on April 16, while just falling to 5A Basic 12-11 on April 18.

Library gearing up for summer

This May we have some wonderful programs coming to the library, including the kickoff to the much-anticipated 2026 Summer Reading Program.

Clean, clean Boulder City

Saturday, volunteers got a 7 a.m. start for Shine Boulder City, hosted by Main Street Boulder City. The clean-up was an initiative through American 250 Nevada. Volunteers helped clean statues, benches and some business exteriors within the Historic Downtown District.

A weekend of art

This past weekend, the Boulder City Art Guild hosted its annual Artists in Action show and sale at the Boulder City Parks and Rec gym. While members do not have to live in Boulder City, all participants must be members of the Art Guild. Top, Boulder City artist Barbara Pearce uses a dotting technique to paint images onto rocks. Below, Ernie Valdovinos sculpts a rabbit from clay.

A busy spring at Mitchell

As always, the leaders at Mitchell have been busy.