Parkway project underway

The long-awaited complete Streets project to improve Boulder City Parkway began Monday and is expected to continue for 10 months.

The $17.5 million project will renovate the street and sidewalks on Boulder City Parkway from Buchanan Boulevard to Veterans Memorial Drive to be safer and more aesthetically pleasing by installing landscaped medians, pedestrian crossings, curbs, gutters, sidewalks and driveways. Upgrades will be made to the sewer main and water systems, including installing new fire hydrants and an irrigation system.

“There will be lane closures to facilitate the work,” City Engineer Jim Keane said. “Access will be provided to all businesses during construction. We divided the project into smaller phases so that the whole corridor from Veterans Memorial Drive to Buchanan Boulevard is not under construction all at once for the … duration of the project.”

Keane said the first of the 10 phases for the project will start at Veterans Memorial Drive and end at the Rebel station on the south side of Boulder City Parkway.

The city is responsible for $596,780 of the project, which includes the sewer and water system improvements, new fire hydrants and amenities such as bike racks, benches and trash cans.

The Nevada Department of Transportation and Regional Transportation Commission of Southern Nevada are responsible for the rest of the project’s cost.

The guaranteed maximum cost for construction is about $15.9 million, according to construction manager American Civil Constructors, which does business as Meadow Valley Contractors. These costs will be covered by RTC.

NDOT is providing $640,000 for more in-depth repairs to the asphalt on the stretch of Boulder City Parkway included in the project.

“Most of the existing asphalt will be a 1-inch mill and overlay, but there will be portions with complete reconstruction where the pavement is failing,” Public Works Director Keegan Littrell said.

The median that will be installed between Veterans Memorial Drive and Gingerwood Street will have metal sculptures, similar to the ones at the Interstate 11-U.S. Highway 95 interchange that depict the life of the Hoover Dam workers in the 1930s. A statue of the Hoover Dam mascot, a black dog that belonged to everyone who worked on the dam, will be installed.

Contact reporter Celia Shortt Goodyear at cgoodyear@bouldercityreview.com or at 702-586-9401. Follow her on Twitter @csgoodyear.

MOST READ
LISTEN TO THE TOP FIVE HERE
THE LATEST
Doubles teams lift Lady Eagles

Sitting with a 3-2-1 record, Boulder City High School girls tennis rebounded nicely after tying with rival Moapa Valley 9-9 on Sept. 3, crushing 4A Silverado 15-3 on Sept. 8.

Church to host Sept. 11 event

As a way to honor those who lost their lives on Sept. 11, 2001, Calvary Chapel of Boulder City will be hosting an event to do just that.

Lady Eagles unbeaten; move to 3-0-1 record

Off to a strong start, Boulder City High School girls soccer enters the week with a 3-0-1 record, following a big win against Equipo Academy on Sept. 3.

Eagles dominate 4A foe on the road

Sitting with a 5-1 record, Boulder City High School boys tennis is performing exactly how head coach Rachelle Huxford expects her championship-quality team to perform.

Boulder City Hospital awarded $2.6M grant

The Boulder City Hospital last week received a pleasant surprise. Actually, more than 2.6 million surprises to be exact.

Understanding Boulder City’s electrical rates

“The city held rates as low as it could for as long as it could.”

State of emergency

My favorite memories as a Boy Scout and church youth group leader always seem to center on community service opportunities.

A game for Grayson

Years from now, the coaches and players on the Boulder City High School varsity football team won’t remember the score of last Friday’s home game. They won’t remember how many yards they ran for or the number of tackles they tallied.