93°F
weather icon Cloudy

Increased costs bedevil BC

It wasn’t just the price of eggs that went up.

You may have noticed recently that the national media has been full of questions about why the “vibe” of the electorate is so negative given that many of the statistics used by economists point to a relatively rosy picture. And, while the rate of inflation is down (although, it bumped back up a little bit in December) the effects are very much still here. One widely-cited study showed that a typical full-ish grocery cart that had a price tag of $100 in late 2019 will cost you more than $125 in January of 2024.

And it’s not just groceries. A number of city projects have been re-thought, somewhat delayed or even put on a “foreseeable future” hold due to rising costs.

The most recent example came in the city council meeting of Jan. 9 when members got an update on planned capital improvement spending and it was reported by the city’s finance department that, as a result of updated quotes on several projects, costs are projected to increase by $623,682.

Three of those projects are related to water conservation. When the initial capital spending plan was distributed, quotes for those projects were not available, so they were put into the plan at a level of $1. The actual cost of those projects will be $260,000.

Over at BCPD, a plan to upgrade the radios used by the department was slated to come out of general operating expenses. However, the quote came back higher than expected, so the radios have moved to the general capital improvement pot at a cost of $120,000.

Out at the two city-run golf courses, planned replacement of various pieces of equipment, including golf carts, is looking to run at least $120,000 more than originally budgeted.

At the Boulder City Fire Department, while plans for a new training facility appear to still be on track, plans for a second fire substation are on indefinite hold after projected costs more than doubled.

Speaking to the council as part of his annual report at their last meeting on Sept. 12, Fire Chief William Gray laid out the entire situation, saying that, while there had originally been an issue finding a company willing to bid on the project, the project appeared to be on track through the summer.

“All the way through June, during the design process, they were optimistic they would be on budget and on time,” he said. “And then in July, our $1.6 million budget came back as maybe $1.9 million. We were able to figure that out. And then, like three weeks later, it came in at $3.6 million. We can’t figure that out.”

Not all of the issues with the substation were general inflation, as the cost to install utility infrastructure on the site originally proposed came with an unexpectedly high price tag of nearly $1 million all by itself.

“Being creative is what we are trying to do right now,” Gray told the council in September. “Potentially remodeling the facility or picking a different piece of land, just looking at all of those options.”

As he called up a picture of the drawings for the planned substation, Gray said, “There are some pictures of what it would have been,” noting that the pictures had been put into the annual report prior to the department having received the latest cost estimates. “It could still be this, we just don’t know.”

Higher costs and long wait times have bedeviled other projects as well, including new playground equipment for several city parks and the decision to replace a worn-out city ambulance with a refurbished box on a new frame in order to save more than $100,000 and to avoid the two- to four-year delay that would be involved with having a new rescue unit built from the ground up.

The major headline story about increased costs last year was the long-simmering plan to replace the aging and largely decrepit city pool.

In their Aug. 8 meeting, the Boulder City Council got a presentation updating estimated costs for a proposed new facility. When the council received the initial estimate from SCA Design in 2021, the cost of replacing the entire facility was tagged at more than $27 million. At the end of February of last year, after receiving an update on conceptual plans and potential costs, the council directed city staff to seek an update to the original cost estimate accounting for what was assumed would be higher costs.

That updated estimate came in at $36.7 million, a whopping 36% increase over the 2021 estimate.

And, keep in mind that that estimate is now almost six months old and inflation may have slowed, but it has not stopped or reversed.

A representative of SCA Design gave a presentation at which she outlined the parameters of the proposed project that had been presented to the Municipal Pool Ad Hoc Committee, which recommended that the city move forward with the project.

“Given the state of the world economy, the United States economy and specifically here in Boulder City, you’re going to see quite a bit of a cost difference,” she said.

MOST READ
LISTEN TO THE TOP FIVE HERE
THE LATEST
Teamwork stressed for BC’s public schools

When walking into the Boulder City High School cafeteria last Wednesday, it was almost like stepping back in time nearly 100 years.

Lady Eagles have lofty season expectations

Featuring a roster full of key returnees, Boulder City High School girls volleyball is looking to make an extended postseason run this season.

Plenty of questions surround champs

Coming off a state championship, Boulder City High School girls tennis is coming into the season with some question marks.

 
Lake Mead sets a record low. It’s only the beginning

For a few hours on Friday, the reservoir that provides nearly all of Southern Nevada’s drinking water dipped to its lowest level ever since it was filled in the 1930s.

Giving back

Saturday evening, Calvary Chapel Boulder City hosted a back-to-school event at Veterans Memorial Park. There, free school supplies and clothing were given out to families. In addition, toys were raffled off, there were free hamburgers, live music and an appearance by the Boulder City Fire Department. Pastor Jason King said he was very happy with the turnout and wished to thank all of those who donated to the event.

Now, that’s a really good idea !

We generally expect our leaders to be educated, smart, and well-informed. More often than not, we support, elect, and follow those who appear to have an answer for everything. But good leaders don’t know everything. And the very best ones know that they don’t know everything.

Sound decisions keep Boulder City costs down

Boulder City residents occasionally ask how the city is able to have one of the lowest property tax rates in the state, and still provide needed functions such as police, fire, and public parks. In addition to land leases that provide 35% of our general fund budget, we also look at ways to keep costs down. As the city’s Purchasing, Grants and Risk manager for the last eight years, I have seen the city make decisions that keep us lean.

Renovation begins on former Milo’s

For those driving through town, it’s hard to miss work on what will be a new Italian eatery in a very iconic location of Restaurant Row, which was once owned and operated by the late Milo Hurst, who helped revitalize Boulder City’s downtown area.

Boulder Theatre to open its doors to events

Whether as a location for builders of Hoover Dam to escape the heat, a place to see movies with families, friends or a date, or a venue to enjoy ballet performances, the Boulder Theatre has been a favorite local historical landmark for nearly a century.