54°F
weather icon Cloudy

Increased costs bedevil BC

It wasn’t just the price of eggs that went up.

You may have noticed recently that the national media has been full of questions about why the “vibe” of the electorate is so negative given that many of the statistics used by economists point to a relatively rosy picture. And, while the rate of inflation is down (although, it bumped back up a little bit in December) the effects are very much still here. One widely-cited study showed that a typical full-ish grocery cart that had a price tag of $100 in late 2019 will cost you more than $125 in January of 2024.

And it’s not just groceries. A number of city projects have been re-thought, somewhat delayed or even put on a “foreseeable future” hold due to rising costs.

The most recent example came in the city council meeting of Jan. 9 when members got an update on planned capital improvement spending and it was reported by the city’s finance department that, as a result of updated quotes on several projects, costs are projected to increase by $623,682.

Three of those projects are related to water conservation. When the initial capital spending plan was distributed, quotes for those projects were not available, so they were put into the plan at a level of $1. The actual cost of those projects will be $260,000.

Over at BCPD, a plan to upgrade the radios used by the department was slated to come out of general operating expenses. However, the quote came back higher than expected, so the radios have moved to the general capital improvement pot at a cost of $120,000.

Out at the two city-run golf courses, planned replacement of various pieces of equipment, including golf carts, is looking to run at least $120,000 more than originally budgeted.

At the Boulder City Fire Department, while plans for a new training facility appear to still be on track, plans for a second fire substation are on indefinite hold after projected costs more than doubled.

Speaking to the council as part of his annual report at their last meeting on Sept. 12, Fire Chief William Gray laid out the entire situation, saying that, while there had originally been an issue finding a company willing to bid on the project, the project appeared to be on track through the summer.

“All the way through June, during the design process, they were optimistic they would be on budget and on time,” he said. “And then in July, our $1.6 million budget came back as maybe $1.9 million. We were able to figure that out. And then, like three weeks later, it came in at $3.6 million. We can’t figure that out.”

Not all of the issues with the substation were general inflation, as the cost to install utility infrastructure on the site originally proposed came with an unexpectedly high price tag of nearly $1 million all by itself.

“Being creative is what we are trying to do right now,” Gray told the council in September. “Potentially remodeling the facility or picking a different piece of land, just looking at all of those options.”

As he called up a picture of the drawings for the planned substation, Gray said, “There are some pictures of what it would have been,” noting that the pictures had been put into the annual report prior to the department having received the latest cost estimates. “It could still be this, we just don’t know.”

Higher costs and long wait times have bedeviled other projects as well, including new playground equipment for several city parks and the decision to replace a worn-out city ambulance with a refurbished box on a new frame in order to save more than $100,000 and to avoid the two- to four-year delay that would be involved with having a new rescue unit built from the ground up.

The major headline story about increased costs last year was the long-simmering plan to replace the aging and largely decrepit city pool.

In their Aug. 8 meeting, the Boulder City Council got a presentation updating estimated costs for a proposed new facility. When the council received the initial estimate from SCA Design in 2021, the cost of replacing the entire facility was tagged at more than $27 million. At the end of February of last year, after receiving an update on conceptual plans and potential costs, the council directed city staff to seek an update to the original cost estimate accounting for what was assumed would be higher costs.

That updated estimate came in at $36.7 million, a whopping 36% increase over the 2021 estimate.

And, keep in mind that that estimate is now almost six months old and inflation may have slowed, but it has not stopped or reversed.

A representative of SCA Design gave a presentation at which she outlined the parameters of the proposed project that had been presented to the Municipal Pool Ad Hoc Committee, which recommended that the city move forward with the project.

“Given the state of the world economy, the United States economy and specifically here in Boulder City, you’re going to see quite a bit of a cost difference,” she said.

THE LATEST
BCHS students win robotics competition

A trip to the workshop for the High Scalers, the robotics team at Boulder City High School in 2024 was much like a visit in 2023. Stuff used to make and practice with the robots built by the team everywhere, six or seven kids gathered there after school and a faculty advisor ensconced in the back of the room at a desk.

Mays in as interim city manager

May 8. That is City Manager Taylour Tedder’s last day working for Boulder City. In other words, Tuesday was Tedder’s final city council meeting.

Council establishes separate pool fund

Things appear to be heating up in terms of motion toward at least initial steps in Boulder City building a new pool. Those steps are not anything that residents will see for a while, but they set the stage.

BCPD closes graffiti case

Thanks to business surveillance cameras, the city’s vigilant license plate reader and “good old-fashioned detective work,” one of the most visible crimes the city has seen this year was solved and arrests made.

Ethics article on hold

In last week’s article on former Boulder City Fire Chief Will Gray’s termination, it mentioned that a follow-up on the Nevada Ethics Commission complaint filed by Gray against Councilman Steve Walton would appear in this week’s edition.

Student Council shines with 2 awards

The Boulder City High School Student Council received a pair of prestigious awards within the past two weeks to add to the list already on their proverbial mantle.

Former fire chief Gray discusses termination

The past few weeks have been a whirlwind for the city, and specifically the fire department, as questions of whether or not Will Gray was still employed as that department’s chief spread through town.

Breeding proposal breeds opposition

Judging by the number of people speaking out against it during public comment at the last city council meeting and the tone of numerous social media posts, the proposal to allow for licensed pet breeders to operate in Boulder City is itself breeding a growing opposition. And the opposition appears to be spilling over into other pet-centric issues, including the fact that, unlike anywhere else in Clark County, Boulder City does not require dogs to be on a leash in public.

Wanted: A good home for theater seats

For those who have either grown up in Boulder City or are longtime residents, the Boulder City Theatre holds a special place in the hearts of many.

Hangars and OHVs and pool people, oh my

In a meeting with only two council members present in the room (and the other three on the phone) and in which the major attention was divided between a contentious possible law concerning pets and the fact that the city manager had announced he was leaving for a new job on the East Coast, the council did take a series of other notable actions.