Leaky part delays transformer installation

A faulty part has delayed the installation of Boulder City’s new backup transformer by one year.

A leak in the new transformer was discovered in July, four months after its arrival, and staff contacted the manufacturer, according to Lisa LaPlante, the city’s communications manager.

“One of the manufactured parts needed to be replaced with a new manufactured part, which took several weeks to complete,” she said. “Once the manufacturer received the part, the city was notified the part was incorrect and another one had to be manufactured.”

The new part was installed in January. Staff tested it to ensure it does not leak and the part passed inspection, LaPlante said. Until the transformer was complete and ready to use, the city held on to part of the payment to the manufacturer, Virginia Transformer.

The new transformer, which costs $1.1 million and weighs about 109 tons, will increase the reliability of the city’s electrical system.

“The next step is to complete the bid package for the above-grade construction portion of the project,” LaPlante said. “We are currently completing our 100 percent plans and specifications review and plan to advertise for construction this spring. ”

The new backup transformer is now expected to be operational in October. The delay has not caused an increase in cost.

Though the transformer, which will serve as the backup to the main electrical system, is ready for the next step for installation, the city has chosen to delay the process to get through the hot summer months.

If the existing transformer is disconnected from the Western Area Power Administration and there were any issues installing the new transformer, the city would be left without any backup to its power-supplying system.

In addition to the transformer, the city will be installing a new circuit breaker and other items for the system, which were purchased earlier.

“City staff has determined that starting phase 2 of the project now, this close to summer, is needlessly risky. … The better course of action is to continue to rely on the old transformer for backup power this summer and to commence breaker replacement starting in October 2019,” LaPlante said.

In 2017, then-Public Works Director Scott Hansen said the process to replace the more than 50-year-old transformer would not affect daily service for the city’s electrical customers. It would, however, be critical to serve the community should there be a problem with the city’s primary power source at the Mead Substation.

When the new transformer was delivered in April 2018, Rory Dwyer, who was the city’s electric utility administrator, said the existing backup does not have the capacity to deliver the large amount of energy needed during the summer.

According to LaPlante, the city holds a five-year warranty on the new transformer, which began now that the final payment has been released.

Contact reporter Celia Shortt Goodyear at cgoodyear@bouldercityreview.com or at 702-586-9401. Follow her on Twitter @csgoodyear.

MOST READ
THE LATEST
Asst. chief discusses hurricane devastation

As the assistant fire chief for the Boulder City Fire department, Josh Barrone has seen his fair share of tragedies and destruction during his career.

City agrees to purchase vehicle barriers

It’s been talked about that thing called a “consent agenda” before. It’s the part of a city council meeting when multiple issues are addressed with a single up or down vote with no discussion of the individual items on the list.

Author’s journey from Boulder City to Ukraine

Twenty years ago, Bill McCormick made a decision and since then has never looked back as he’s turned what is a hobby for some into a full-time profession.

BC first responders honored

On Tuesday evening, nine members of the Boulder City Fire Departments and one BCPD detective were honored by the city’s two Rotary clubs as part of their Service Officer Award Recognition program, which celebrates first responders who are “everyday heroes.”

Doc loses license for 5 years

A Boulder City chiropractor has lost his license to practice in the state for five years, which could be extended if he does not adhere to requirements voted upon by the Chiropractic Physicians’ Board of Nevada.

Dog park slated to reopen Oct. 31

Before the mayor cut the ribbon on a city-funded dog park with grass inside Veterans’ Memorial Park in August of last year, Boulder City was the only municipality in the region not to have such a facility. (See Spot Run is just a stone’s throw away but it is privately run and does not have grass.)

An educational leap of faith

Something new recently opened in Boulder City, which brought with it a bit of a twist to traditional education.