72°F
weather icon Windy

Leaky part delays transformer installation

A faulty part has delayed the installation of Boulder City’s new backup transformer by one year.

A leak in the new transformer was discovered in July, four months after its arrival, and staff contacted the manufacturer, according to Lisa LaPlante, the city’s communications manager.

“One of the manufactured parts needed to be replaced with a new manufactured part, which took several weeks to complete,” she said. “Once the manufacturer received the part, the city was notified the part was incorrect and another one had to be manufactured.”

The new part was installed in January. Staff tested it to ensure it does not leak and the part passed inspection, LaPlante said. Until the transformer was complete and ready to use, the city held on to part of the payment to the manufacturer, Virginia Transformer.

The new transformer, which costs $1.1 million and weighs about 109 tons, will increase the reliability of the city’s electrical system.

“The next step is to complete the bid package for the above-grade construction portion of the project,” LaPlante said. “We are currently completing our 100 percent plans and specifications review and plan to advertise for construction this spring. ”

The new backup transformer is now expected to be operational in October. The delay has not caused an increase in cost.

Though the transformer, which will serve as the backup to the main electrical system, is ready for the next step for installation, the city has chosen to delay the process to get through the hot summer months.

If the existing transformer is disconnected from the Western Area Power Administration and there were any issues installing the new transformer, the city would be left without any backup to its power-supplying system.

In addition to the transformer, the city will be installing a new circuit breaker and other items for the system, which were purchased earlier.

“City staff has determined that starting phase 2 of the project now, this close to summer, is needlessly risky. … The better course of action is to continue to rely on the old transformer for backup power this summer and to commence breaker replacement starting in October 2019,” LaPlante said.

In 2017, then-Public Works Director Scott Hansen said the process to replace the more than 50-year-old transformer would not affect daily service for the city’s electrical customers. It would, however, be critical to serve the community should there be a problem with the city’s primary power source at the Mead Substation.

When the new transformer was delivered in April 2018, Rory Dwyer, who was the city’s electric utility administrator, said the existing backup does not have the capacity to deliver the large amount of energy needed during the summer.

According to LaPlante, the city holds a five-year warranty on the new transformer, which began now that the final payment has been released.

Contact reporter Celia Shortt Goodyear at cgoodyear@bouldercityreview.com or at 702-586-9401. Follow her on Twitter @csgoodyear.

MOST READ
LISTEN TO THE TOP FIVE HERE
THE LATEST
Boys volleyball wins first league game

Boulder City High School started league play with a victory, defeating The Meadows 3-0 on April 1.

From Garden to Grave

Last week, the Christian Center Church hosted four showings of Garden to Grave: Live Stations of the Cross. Pastor Deborah Downs said the Stations of the Cross “are a contemplative practice of walking the way of suffering with Jesus. If one were to visit the city of Jerusalem, they would discover all 14 stations on what is called the Via Dolorosa – The Sorrowful Way – a path from Pilate’s court to Golgotha to the tomb.”

Community gives input on possible consolidations

Dozens of parents, teachers, administrators and a handful of students turned out last Wednesdays for the first of two public meetings to discuss possible school consolidations.

Early risers

Photos by Ron Eland/Boulder City Review

What’s on the table

While changes can be made between now and when the CCSD Board makes its decision this fall, here are the potential options from the Facility Master Plan for public schools in Boulder City:

Jenas-Keogh shines again on track

Competing in a home weekday event on April 1, Boulder City High School girls track and field showed why they should be considered a real threat in the 3A classification.

Eagles continue to win on the diamond

Boulder City High School baseball has started league play off hot, sweeping a series with The Meadows this past week.

Challenging (budget) forecast ahead

Have you ever called for emergency services in Boulder City? Did you know that on medical calls, the fire department typically sends two or more first responders? The American Heart Association recommends one responder manages the patient’s airway; another monitors cardiac activity; another is responsible for administering medication; and two provide cardiopulmonary resuscitation (CPR) or lift assists as needed. On a heart attack or stroke, up to six responders may be needed.

Sylvanie case gets 30-day continuance

The preliminary hearing for longtime Boulder City resident Terry Sylvanie was continued Tuesday, with a possible resolution the next time he appears in Boulder City Justice Court.