60°F
weather icon Clear

Leaky part delays transformer installation

A faulty part has delayed the installation of Boulder City’s new backup transformer by one year.

A leak in the new transformer was discovered in July, four months after its arrival, and staff contacted the manufacturer, according to Lisa LaPlante, the city’s communications manager.

“One of the manufactured parts needed to be replaced with a new manufactured part, which took several weeks to complete,” she said. “Once the manufacturer received the part, the city was notified the part was incorrect and another one had to be manufactured.”

The new part was installed in January. Staff tested it to ensure it does not leak and the part passed inspection, LaPlante said. Until the transformer was complete and ready to use, the city held on to part of the payment to the manufacturer, Virginia Transformer.

The new transformer, which costs $1.1 million and weighs about 109 tons, will increase the reliability of the city’s electrical system.

“The next step is to complete the bid package for the above-grade construction portion of the project,” LaPlante said. “We are currently completing our 100 percent plans and specifications review and plan to advertise for construction this spring. ”

The new backup transformer is now expected to be operational in October. The delay has not caused an increase in cost.

Though the transformer, which will serve as the backup to the main electrical system, is ready for the next step for installation, the city has chosen to delay the process to get through the hot summer months.

If the existing transformer is disconnected from the Western Area Power Administration and there were any issues installing the new transformer, the city would be left without any backup to its power-supplying system.

In addition to the transformer, the city will be installing a new circuit breaker and other items for the system, which were purchased earlier.

“City staff has determined that starting phase 2 of the project now, this close to summer, is needlessly risky. … The better course of action is to continue to rely on the old transformer for backup power this summer and to commence breaker replacement starting in October 2019,” LaPlante said.

In 2017, then-Public Works Director Scott Hansen said the process to replace the more than 50-year-old transformer would not affect daily service for the city’s electrical customers. It would, however, be critical to serve the community should there be a problem with the city’s primary power source at the Mead Substation.

When the new transformer was delivered in April 2018, Rory Dwyer, who was the city’s electric utility administrator, said the existing backup does not have the capacity to deliver the large amount of energy needed during the summer.

According to LaPlante, the city holds a five-year warranty on the new transformer, which began now that the final payment has been released.

Contact reporter Celia Shortt Goodyear at cgoodyear@bouldercityreview.com or at 702-586-9401. Follow her on Twitter @csgoodyear.

MOST READ
LISTEN TO THE TOP FIVE HERE
THE LATEST
New plan for former Vons

For several years, the former Vons building on Boulder City Parkway has sat empty. But a big step was taken last week to change that.

Council gives Thomas high six-month marks

At just more than six months on the job, City Manager Ned Thomas does not need to be worried about keeping the gig as city council members gathered Wednesday morning for an earlier-than-normal performance evaluation and every comment from every member present (Councilwoman Sherri Jorgensen was absent) could be fairly characterized as stellar.

City votes to join regional council

If one is offered an equal seat at the table on a regional group that advises on policy for an area where that person’s population is equal to .005% of the total region at a cost of $5,000 per year, does that sound like a pretty good deal?

BCPD awarded traffic safety grants

Boulder City Police Department will, once again, be participating in the Joining Forces traffic safety campaign. More than 30 law enforcement agencies across the state of Nevada will team up to focus on traffic safety awareness and enforcement. The campaign series will run from October 2025 through September 2026.

More RV storage? Council approves appraisal for possible future project

The old Vons building is not the only place in the mix for future RV storage. (See story on page 1.) The city is also eyeing a possible future facility in the area where Veterans Memorial Drive and Yucca Street come together.

BCHS takes part in earthquake drill

In a way, it had that Cold War-era feel to it when students a half-century ago were trained to duck and take cover under their desks in the event of a nuclear bomb attack.

Enjoying a (National) Night Out

Photos by Ron Eland/Boulder City Review

Say hello to Liberty Ridge

So, no more Tract 350. Not the project but rather the name.

City pleased with Nevada Way project

It’s been a few weeks since the completion of the roadwork on Nevada Way, and according to the city, they’re happy with the finished product.