Street paving project underway

Work to repave several streets within Boulder City will begin soon as part of the 2016-2017 slurry seal maintenance project.

Public Works Director Scott Hansen said that Morgan Pavement Maintenance began Monday and will continue for approximately two months on various streets within the city. The company has already placed signs notifying residents about the project throughout streets in downtown Boulder City.

“Work will include site preparation, property owner notification, traffic control, crack sealing, slurry seal pavement overlay and cleanup,” Hansen said.

Streets to be worked on as part of the project include: Industrial, Buchanan, Joshua, Fir, Date, Railroad, Birch, Cherry, Ash, Avenue A, Avenue B, Aztec, and Hotel Plaza.

“The contract is for 60 days, so all work should be done by the end of July,” Hansen said.

The specific dates for road closures were not available and Morgan Pavement did not respond requests for this information.

MOST READ
LISTEN TO THE TOP FIVE HERE
THE LATEST
Eagles pick up two key wins

Building a winning streak before the postseason, Boulder City High School baseball picked up victories this past week over Laughlin and White Pine.

Visitor center still on track

For those who drive by the soon-to-be completed Nevada State Railroad Museum Visitor Center, it’s hard not to see something new with each passing.

Volleyball squad undefeated in league

Remaining atop the 3A standings, Boulder City High School boys volleyball won a pair of league games this past week to advance to 7-0 in league play.

Thomas looks back at first year

With just about any new job, especially within a municipality, there’s a learning curve as one gets to know the issues and the people.

Boulder City Ambassadors

Photos by Ron Eland/Boulder City Review

Elections with love

I was happy to see that Boulder City is going to have an election that provides time for both communicating as well as understanding. It is unresolved until Tuesday, Nov. 3, 2026. Choices for city council should never be ignored or hurried. Our duty as citizens is to objectively apply the best information we have to decide for whom to vote.

Residential Amnesty Program starts May 1

Imagine getting ready to sell your house, or worse yet, have a disaster in the home, only to find out an earlier renovation or remodel was not up to code? Modifications can bring a home sale to a grinding halt, or cause problems for insurance reimbursement. If you renovated or remodeled your home or accessory structure without getting a building permit first, here is your opportunity to get in compliance.