57°F
weather icon Clear

Leaky part delays transformer installation

A faulty part has delayed the installation of Boulder City’s new backup transformer by one year.

A leak in the new transformer was discovered in July, four months after its arrival, and staff contacted the manufacturer, according to Lisa LaPlante, the city’s communications manager.

“One of the manufactured parts needed to be replaced with a new manufactured part, which took several weeks to complete,” she said. “Once the manufacturer received the part, the city was notified the part was incorrect and another one had to be manufactured.”

The new part was installed in January. Staff tested it to ensure it does not leak and the part passed inspection, LaPlante said. Until the transformer was complete and ready to use, the city held on to part of the payment to the manufacturer, Virginia Transformer.

The new transformer, which costs $1.1 million and weighs about 109 tons, will increase the reliability of the city’s electrical system.

“The next step is to complete the bid package for the above-grade construction portion of the project,” LaPlante said. “We are currently completing our 100 percent plans and specifications review and plan to advertise for construction this spring. ”

The new backup transformer is now expected to be operational in October. The delay has not caused an increase in cost.

Though the transformer, which will serve as the backup to the main electrical system, is ready for the next step for installation, the city has chosen to delay the process to get through the hot summer months.

If the existing transformer is disconnected from the Western Area Power Administration and there were any issues installing the new transformer, the city would be left without any backup to its power-supplying system.

In addition to the transformer, the city will be installing a new circuit breaker and other items for the system, which were purchased earlier.

“City staff has determined that starting phase 2 of the project now, this close to summer, is needlessly risky. … The better course of action is to continue to rely on the old transformer for backup power this summer and to commence breaker replacement starting in October 2019,” LaPlante said.

In 2017, then-Public Works Director Scott Hansen said the process to replace the more than 50-year-old transformer would not affect daily service for the city’s electrical customers. It would, however, be critical to serve the community should there be a problem with the city’s primary power source at the Mead Substation.

When the new transformer was delivered in April 2018, Rory Dwyer, who was the city’s electric utility administrator, said the existing backup does not have the capacity to deliver the large amount of energy needed during the summer.

According to LaPlante, the city holds a five-year warranty on the new transformer, which began now that the final payment has been released.

Contact reporter Celia Shortt Goodyear at cgoodyear@bouldercityreview.com or at 702-586-9401. Follow her on Twitter @csgoodyear.

MOST READ
LISTEN TO THE TOP FIVE HERE
THE LATEST
Eagles dominate competition in pool

On the hunt for their fourth consecutive 3A state championship, Boulder City High School boys swimming didn’t disappoint in their season opener at Heritage on Feb. 28, defeating Coral Academy 640-333.

Eagles look for another state title on court

With their eyes on recapturing the 3A state title, Boulder City High School boys volleyball challenged themselves early with some stiff competition in the Las Vegas Invitational.

Track and field teams off to strong start

Competing at the a Liberty Newcomer meet on Feb. 26, multiple new faces for Boulder City High School track and field got the opportunity to showcase their abilities.

Shakespeare returns to Boulder City

Lovers of William Shakespeare need to mark March 13 on their calendars.

Council incumbents plan to seek re-election

Monday was the first opportunity for residents to file as candidates in this year’s Boulder City Council election.

Trio of Boulder High athletes sign with colleges

Fulfilling their dreams of becoming collegiate athletes, three Boulder City High seniors, Logan Borg, Cameron Matthews and Preston Van Beveren will be heading off to their respective universities next fall.

N.Y. man drives through power plant fence

This past Friday, LVMPD Sheriff Kevin McMahill, along with the FBI Special Agent in Charge Christopher Delzotto of the Las Vegas Field Office and Timothy Shea, Chief of the Boulder City Police Department, provided details regarding a vehicle ramming a power facility outside of Boulder City.

Lady Eagles lose to state champions

Boulder City High School girls basketball may have fallen to eventual state champion Churchill County in the state tournament, 56-17, on Feb. 20, but coach Brian Bradshaw’s Eagles took more away from the experience than just a loss.