53°F
weather icon Windy

Leaky part delays transformer installation

A faulty part has delayed the installation of Boulder City’s new backup transformer by one year.

A leak in the new transformer was discovered in July, four months after its arrival, and staff contacted the manufacturer, according to Lisa LaPlante, the city’s communications manager.

“One of the manufactured parts needed to be replaced with a new manufactured part, which took several weeks to complete,” she said. “Once the manufacturer received the part, the city was notified the part was incorrect and another one had to be manufactured.”

The new part was installed in January. Staff tested it to ensure it does not leak and the part passed inspection, LaPlante said. Until the transformer was complete and ready to use, the city held on to part of the payment to the manufacturer, Virginia Transformer.

The new transformer, which costs $1.1 million and weighs about 109 tons, will increase the reliability of the city’s electrical system.

“The next step is to complete the bid package for the above-grade construction portion of the project,” LaPlante said. “We are currently completing our 100 percent plans and specifications review and plan to advertise for construction this spring. ”

The new backup transformer is now expected to be operational in October. The delay has not caused an increase in cost.

Though the transformer, which will serve as the backup to the main electrical system, is ready for the next step for installation, the city has chosen to delay the process to get through the hot summer months.

If the existing transformer is disconnected from the Western Area Power Administration and there were any issues installing the new transformer, the city would be left without any backup to its power-supplying system.

In addition to the transformer, the city will be installing a new circuit breaker and other items for the system, which were purchased earlier.

“City staff has determined that starting phase 2 of the project now, this close to summer, is needlessly risky. … The better course of action is to continue to rely on the old transformer for backup power this summer and to commence breaker replacement starting in October 2019,” LaPlante said.

In 2017, then-Public Works Director Scott Hansen said the process to replace the more than 50-year-old transformer would not affect daily service for the city’s electrical customers. It would, however, be critical to serve the community should there be a problem with the city’s primary power source at the Mead Substation.

When the new transformer was delivered in April 2018, Rory Dwyer, who was the city’s electric utility administrator, said the existing backup does not have the capacity to deliver the large amount of energy needed during the summer.

According to LaPlante, the city holds a five-year warranty on the new transformer, which began now that the final payment has been released.

Contact reporter Celia Shortt Goodyear at cgoodyear@bouldercityreview.com or at 702-586-9401. Follow her on Twitter @csgoodyear.

MOST READ
LISTEN TO THE TOP FIVE HERE
THE LATEST
Spring Jamboree features something for everyone

If one is looking for an event that checks just about every box to have a fun weekend in Boulder City, the annual Spring Jamboree is just that.

Track teams shine at home meet as girls dominate

Continuing to excel in weekday events, both Boulder City High School track and field programs shined on their home turf.

Private helipad is becoming closer to reality

A request to build a private residential heliport cleared a second hurdle last week during more than an hour-long presentation and discussion.

Longtime resident turning 100

The number of Americans who are 100 years or older is expected to hit 101,000 this year.

Baseball knocks off 5A foe Coronado

Playing inspiring baseball, Boulder City High School knocked off 5A Coronado 10-8 on April 16, while just falling to 5A Basic 12-11 on April 18.

Library gearing up for summer

This May we have some wonderful programs coming to the library, including the kickoff to the much-anticipated 2026 Summer Reading Program.

Clean, clean Boulder City

Saturday, volunteers got a 7 a.m. start for Shine Boulder City, hosted by Main Street Boulder City. The clean-up was an initiative through American 250 Nevada. Volunteers helped clean statues, benches and some business exteriors within the Historic Downtown District.

A weekend of art

This past weekend, the Boulder City Art Guild hosted its annual Artists in Action show and sale at the Boulder City Parks and Rec gym. While members do not have to live in Boulder City, all participants must be members of the Art Guild. Top, Boulder City artist Barbara Pearce uses a dotting technique to paint images onto rocks. Below, Ernie Valdovinos sculpts a rabbit from clay.

A busy spring at Mitchell

As always, the leaders at Mitchell have been busy.