75°F
weather icon Clear

Leaky part delays transformer installation

A faulty part has delayed the installation of Boulder City’s new backup transformer by one year.

A leak in the new transformer was discovered in July, four months after its arrival, and staff contacted the manufacturer, according to Lisa LaPlante, the city’s communications manager.

“One of the manufactured parts needed to be replaced with a new manufactured part, which took several weeks to complete,” she said. “Once the manufacturer received the part, the city was notified the part was incorrect and another one had to be manufactured.”

The new part was installed in January. Staff tested it to ensure it does not leak and the part passed inspection, LaPlante said. Until the transformer was complete and ready to use, the city held on to part of the payment to the manufacturer, Virginia Transformer.

The new transformer, which costs $1.1 million and weighs about 109 tons, will increase the reliability of the city’s electrical system.

“The next step is to complete the bid package for the above-grade construction portion of the project,” LaPlante said. “We are currently completing our 100 percent plans and specifications review and plan to advertise for construction this spring. ”

The new backup transformer is now expected to be operational in October. The delay has not caused an increase in cost.

Though the transformer, which will serve as the backup to the main electrical system, is ready for the next step for installation, the city has chosen to delay the process to get through the hot summer months.

If the existing transformer is disconnected from the Western Area Power Administration and there were any issues installing the new transformer, the city would be left without any backup to its power-supplying system.

In addition to the transformer, the city will be installing a new circuit breaker and other items for the system, which were purchased earlier.

“City staff has determined that starting phase 2 of the project now, this close to summer, is needlessly risky. … The better course of action is to continue to rely on the old transformer for backup power this summer and to commence breaker replacement starting in October 2019,” LaPlante said.

In 2017, then-Public Works Director Scott Hansen said the process to replace the more than 50-year-old transformer would not affect daily service for the city’s electrical customers. It would, however, be critical to serve the community should there be a problem with the city’s primary power source at the Mead Substation.

When the new transformer was delivered in April 2018, Rory Dwyer, who was the city’s electric utility administrator, said the existing backup does not have the capacity to deliver the large amount of energy needed during the summer.

According to LaPlante, the city holds a five-year warranty on the new transformer, which began now that the final payment has been released.

Contact reporter Celia Shortt Goodyear at cgoodyear@bouldercityreview.com or at 702-586-9401. Follow her on Twitter @csgoodyear.

MOST READ
LISTEN TO THE TOP FIVE HERE
THE LATEST
Preservation Day: A step back in time

Dozens of people had an opportunity to journey back in time and get an inside look into Boulder City’s past as part of Saturday’s annual Historic Preservation Day.

Jenas-Keogh paces girls on track

Putting their best foot forward, Boulder City High School track and field will be well respected at the 3A state meet, qualifying 12 girls and nine boys after this past week’s regional meet.

McClarens lead swimmers to title

Continuing their illustrious pedigree of excellence, Boulder City High School boys and girls swimming each took home 3A regional championships this past weekend.

Eagles finish as top seed from south

Making a return trip to the state tournament, Boulder City High School baseball enters as the top seed out of the south.

Grace Christian Academy set to close after 26 years

For a little more than a quarter century, Grace Christian Academy has offered an alternative to elementary education in Boulder City. But as of the end of this month, its doors will be closed.

That’s good; no, that’s bad

Have you ever noticed how life can feel perfectly calm, and then suddenly everything hits at once? The calm before the storm is a real phenomenon in nature. The atmosphere often becomes extra still and quiet just before a raging storm breaks. And then, when it finally rains, it often pours, as the saying goes.

Garrett excels in classroom, field, stage

Garrett Junior High School has been very busy this quarter. Across campus, classrooms are wrapping up their final projects and concluding MAP testing to bring us into the final few days of the school year.

Something new is afloat in Boulder City

Last week, city staff took the Municipal Pool bubble down for the last time.

Data centers still a hot topic

It’s one of the most discussed topics around town these days: that being the proposed data center in Eldorado Valley, nearly three miles from the nearest residence in Boulder City.