68°F
weather icon Clear

Leaky part delays transformer installation

A faulty part has delayed the installation of Boulder City’s new backup transformer by one year.

A leak in the new transformer was discovered in July, four months after its arrival, and staff contacted the manufacturer, according to Lisa LaPlante, the city’s communications manager.

“One of the manufactured parts needed to be replaced with a new manufactured part, which took several weeks to complete,” she said. “Once the manufacturer received the part, the city was notified the part was incorrect and another one had to be manufactured.”

The new part was installed in January. Staff tested it to ensure it does not leak and the part passed inspection, LaPlante said. Until the transformer was complete and ready to use, the city held on to part of the payment to the manufacturer, Virginia Transformer.

The new transformer, which costs $1.1 million and weighs about 109 tons, will increase the reliability of the city’s electrical system.

“The next step is to complete the bid package for the above-grade construction portion of the project,” LaPlante said. “We are currently completing our 100 percent plans and specifications review and plan to advertise for construction this spring. ”

The new backup transformer is now expected to be operational in October. The delay has not caused an increase in cost.

Though the transformer, which will serve as the backup to the main electrical system, is ready for the next step for installation, the city has chosen to delay the process to get through the hot summer months.

If the existing transformer is disconnected from the Western Area Power Administration and there were any issues installing the new transformer, the city would be left without any backup to its power-supplying system.

In addition to the transformer, the city will be installing a new circuit breaker and other items for the system, which were purchased earlier.

“City staff has determined that starting phase 2 of the project now, this close to summer, is needlessly risky. … The better course of action is to continue to rely on the old transformer for backup power this summer and to commence breaker replacement starting in October 2019,” LaPlante said.

In 2017, then-Public Works Director Scott Hansen said the process to replace the more than 50-year-old transformer would not affect daily service for the city’s electrical customers. It would, however, be critical to serve the community should there be a problem with the city’s primary power source at the Mead Substation.

When the new transformer was delivered in April 2018, Rory Dwyer, who was the city’s electric utility administrator, said the existing backup does not have the capacity to deliver the large amount of energy needed during the summer.

According to LaPlante, the city holds a five-year warranty on the new transformer, which began now that the final payment has been released.

Contact reporter Celia Shortt Goodyear at cgoodyear@bouldercityreview.com or at 702-586-9401. Follow her on Twitter @csgoodyear.

MOST READ
LISTEN TO THE TOP FIVE HERE
THE LATEST
Feds take over Sylvanie case

The case against Boulder City’s Terry Sylvanie took a turn last month when a federal grand jury indicted him on charges of distributing and possessing child sexual abuse images.

CCSD receives more input on master plan

More than 50 parents, educators and interested residents met for round two of discussion regarding Clark County School District’s preliminary draft options for its Facility Master Plan.

Jammin’ at the Jamboree

A member of the Flippenout Trampoline team appears to be walking on air, much to the delight of the crowd.

Eagles finish league play undefeated

Looking to reclaim the 3A state title, Boulder City High School boys volleyball completed their first step, finishing league play with an undefeated record after beating rival Moapa Valley 3-1 on April 29.

Track teams head to regionals Friday

Hosting a small-school invitational on May 1, Boulder City High School girls track and field finished second out of 13 programs, while the boys finished sixth out of 13 schools.

Softball ends regular season by defeating Moapa Valley

Rising to the occasion, Boulder City High School softball defeated rival Moapa Valley 7-3 April 30 to finish the regular season on a high note.

BCHS band performs in Disneyland

There are performances, and then there are moments that become part of the magic.