66°F
weather icon Cloudy

Leaky part delays transformer installation

A faulty part has delayed the installation of Boulder City’s new backup transformer by one year.

A leak in the new transformer was discovered in July, four months after its arrival, and staff contacted the manufacturer, according to Lisa LaPlante, the city’s communications manager.

“One of the manufactured parts needed to be replaced with a new manufactured part, which took several weeks to complete,” she said. “Once the manufacturer received the part, the city was notified the part was incorrect and another one had to be manufactured.”

The new part was installed in January. Staff tested it to ensure it does not leak and the part passed inspection, LaPlante said. Until the transformer was complete and ready to use, the city held on to part of the payment to the manufacturer, Virginia Transformer.

The new transformer, which costs $1.1 million and weighs about 109 tons, will increase the reliability of the city’s electrical system.

“The next step is to complete the bid package for the above-grade construction portion of the project,” LaPlante said. “We are currently completing our 100 percent plans and specifications review and plan to advertise for construction this spring. ”

The new backup transformer is now expected to be operational in October. The delay has not caused an increase in cost.

Though the transformer, which will serve as the backup to the main electrical system, is ready for the next step for installation, the city has chosen to delay the process to get through the hot summer months.

If the existing transformer is disconnected from the Western Area Power Administration and there were any issues installing the new transformer, the city would be left without any backup to its power-supplying system.

In addition to the transformer, the city will be installing a new circuit breaker and other items for the system, which were purchased earlier.

“City staff has determined that starting phase 2 of the project now, this close to summer, is needlessly risky. … The better course of action is to continue to rely on the old transformer for backup power this summer and to commence breaker replacement starting in October 2019,” LaPlante said.

In 2017, then-Public Works Director Scott Hansen said the process to replace the more than 50-year-old transformer would not affect daily service for the city’s electrical customers. It would, however, be critical to serve the community should there be a problem with the city’s primary power source at the Mead Substation.

When the new transformer was delivered in April 2018, Rory Dwyer, who was the city’s electric utility administrator, said the existing backup does not have the capacity to deliver the large amount of energy needed during the summer.

According to LaPlante, the city holds a five-year warranty on the new transformer, which began now that the final payment has been released.

Contact reporter Celia Shortt Goodyear at cgoodyear@bouldercityreview.com or at 702-586-9401. Follow her on Twitter @csgoodyear.

MOST READ
LISTEN TO THE TOP FIVE HERE
THE LATEST
Mark your calendars: A busy December in BC

December in Boulder City is one of those months where there’s often not enough space on one’s calendar to put down all the community events offered.

Las Vegas’ deepest straw at Lake Mead is about to go 30 feet deeper

Divers, cranes and robot submarines will help Southern Nevada lower its Lake Mead intake another 30 feet as officials prepare for a drier Colorado River future. It will cost ratepayers nearly $21 million.

City collecting for the holidays

The city is in the midst of hosting the 20th annual holiday donation drive to lend a helping hand to families and individuals in town.

Shop local for Small Business Saturday

It’s becoming a holiday shopping tradition on par with Black Friday.

Hinds signs on the dotted line for UNLV

Staying home to continue her storied golf career, Boulder City High School phenom Emmerson Hinds has signed with hometown UNLV.

Soccer team earns postseason awards

Following a trip to the 3A state tournament, seven Boulder City High School girls soccer players earned postseason accolades, while head coach Kristin Shelton was named 3A Coach of the Year.

Lady Eagles expect to challenge for title

Coming off a state tournament appearance, Boulder City High School girls basketball expects to compete for a state championship this upcoming season.

Final election results released

During a special city council meeting this past Friday in which the canvassing of the Nov. 3 election was certified and approved, the final voter numbers were presented.