Accelerated timetable may push loop’s phase one

It doesn’t make sense to build the second phase of the Interstate 11 loop without making sure the first phase is completed at the same time to connect.

The first phase of the I-11 loop, formerly known as the Boulder City Bypass, is in the early stages with road construction possibly beginning late this year and taking until nearly the year 2020.

However, with the Regional Transportation Commission of Southern Nevada telling the City Council last week that construction on the second phase could start next fall and finish in 2017, the construction timeline of the connecting phase by Railroad Pass would have to be pushed up.

“It would force us to finish phase one because you can’t have a phase two without that phase one,” said Tony Lorenzi, senior project manager for the Nevada Transportation Department. “It would force us to hurry up and finish our portion.”

Phase one is being overseen by the department and phase two is being administered by the Transportation Commission.

Funding of the $300 million second phase hinges on a proposed fuel-tax increase that needs the approval of the Clark County Commission. If approved, the Transportation Commission would take $700 million to $800 million in bonds that would be paid back with future tax revenue.

Nearly $230 million of that funding would go toward the I-11 loop second phase.

Phase one is the realignment of U.S. Highway 93/95 by Railroad Pass, which would include removing the stoplight in front of the casino. The stoplight can cause traffic back up toward Boulder City during Friday evenings and holiday weekends.

“The main benefit of phase one if the removal of that half-signal,” Lorenzi said. “It’s a very dangerous intersection, it’s a high-crash location.”

Phase one will pull the highway away from the casino, which will improve traffic flow especially for tractor-trailers.

Lorenzi said $32 million in construction of the connector from the Railroad Pass interchange to U.S. 95 where the loop would begin in the phase one plans could move to phase two.

“We’re meeting with the RTC to see how we can integrate phase one into phase two and get the whole (I-11) built,” he said.

The department also meets with the Federal Highway Administration, which is studying an I-11 corridor from Phoenix to Las Vegas.

According to Lorenzi, right-of-way acquisitions are nearly complete with the state attorney general’s office negotiating right-of-way acquisitions for the first phase, including the three-acre portion controlled by Jericho Heights, as well as land held by Railroad Pass Casino and K&L Dirt.

“Our goal is to settle it before it even goes to court,” Lorenzi said. The cost of acquisition, which was budgeted at $20 million to $30 million, could be nearly $60 million.

However, the state does not have to wait for the settlements to be complete before the project can begin road construction.

“We could build the project tomorrow,” Lorenzi said. “It’s just a matter of how much money are those three owners going to get.”

The department began plant salvaging and tortoise fencing in January, a $1.5 million project that should be completed soon.

Lorenzi said more than 20,000 endangered species plants that are being harvested in a nursery off U.S. 95. They will be replanted during the frontage road construction that will go from Foothill to Railroad Pass.

MOST READ
LISTEN TO THE TOP FIVE HERE
THE LATEST
Teamwork stressed for BC’s public schools

When walking into the Boulder City High School cafeteria last Wednesday, it was almost like stepping back in time nearly 100 years.

Lady Eagles have lofty season expectations

Featuring a roster full of key returnees, Boulder City High School girls volleyball is looking to make an extended postseason run this season.

Plenty of questions surround champs

Coming off a state championship, Boulder City High School girls tennis is coming into the season with some question marks.

 
Lake Mead sets a record low. It’s only the beginning

For a few hours on Friday, the reservoir that provides nearly all of Southern Nevada’s drinking water dipped to its lowest level ever since it was filled in the 1930s.

Giving back

Saturday evening, Calvary Chapel Boulder City hosted a back-to-school event at Veterans Memorial Park. There, free school supplies and clothing were given out to families. In addition, toys were raffled off, there were free hamburgers, live music and an appearance by the Boulder City Fire Department. Pastor Jason King said he was very happy with the turnout and wished to thank all of those who donated to the event.

Now, that’s a really good idea !

We generally expect our leaders to be educated, smart, and well-informed. More often than not, we support, elect, and follow those who appear to have an answer for everything. But good leaders don’t know everything. And the very best ones know that they don’t know everything.

Sound decisions keep Boulder City costs down

Boulder City residents occasionally ask how the city is able to have one of the lowest property tax rates in the state, and still provide needed functions such as police, fire, and public parks. In addition to land leases that provide 35% of our general fund budget, we also look at ways to keep costs down. As the city’s Purchasing, Grants and Risk manager for the last eight years, I have seen the city make decisions that keep us lean.

Renovation begins on former Milo’s

For those driving through town, it’s hard to miss work on what will be a new Italian eatery in a very iconic location of Restaurant Row, which was once owned and operated by the late Milo Hurst, who helped revitalize Boulder City’s downtown area.

Boulder Theatre to open its doors to events

Whether as a location for builders of Hoover Dam to escape the heat, a place to see movies with families, friends or a date, or a venue to enjoy ballet performances, the Boulder Theatre has been a favorite local historical landmark for nearly a century.