Accelerated timetable may push loop’s phase one

It doesn’t make sense to build the second phase of the Interstate 11 loop without making sure the first phase is completed at the same time to connect.

The first phase of the I-11 loop, formerly known as the Boulder City Bypass, is in the early stages with road construction possibly beginning late this year and taking until nearly the year 2020.

However, with the Regional Transportation Commission of Southern Nevada telling the City Council last week that construction on the second phase could start next fall and finish in 2017, the construction timeline of the connecting phase by Railroad Pass would have to be pushed up.

“It would force us to finish phase one because you can’t have a phase two without that phase one,” said Tony Lorenzi, senior project manager for the Nevada Transportation Department. “It would force us to hurry up and finish our portion.”

Phase one is being overseen by the department and phase two is being administered by the Transportation Commission.

Funding of the $300 million second phase hinges on a proposed fuel-tax increase that needs the approval of the Clark County Commission. If approved, the Transportation Commission would take $700 million to $800 million in bonds that would be paid back with future tax revenue.

Nearly $230 million of that funding would go toward the I-11 loop second phase.

Phase one is the realignment of U.S. Highway 93/95 by Railroad Pass, which would include removing the stoplight in front of the casino. The stoplight can cause traffic back up toward Boulder City during Friday evenings and holiday weekends.

“The main benefit of phase one if the removal of that half-signal,” Lorenzi said. “It’s a very dangerous intersection, it’s a high-crash location.”

Phase one will pull the highway away from the casino, which will improve traffic flow especially for tractor-trailers.

Lorenzi said $32 million in construction of the connector from the Railroad Pass interchange to U.S. 95 where the loop would begin in the phase one plans could move to phase two.

“We’re meeting with the RTC to see how we can integrate phase one into phase two and get the whole (I-11) built,” he said.

The department also meets with the Federal Highway Administration, which is studying an I-11 corridor from Phoenix to Las Vegas.

According to Lorenzi, right-of-way acquisitions are nearly complete with the state attorney general’s office negotiating right-of-way acquisitions for the first phase, including the three-acre portion controlled by Jericho Heights, as well as land held by Railroad Pass Casino and K&L Dirt.

“Our goal is to settle it before it even goes to court,” Lorenzi said. The cost of acquisition, which was budgeted at $20 million to $30 million, could be nearly $60 million.

However, the state does not have to wait for the settlements to be complete before the project can begin road construction.

“We could build the project tomorrow,” Lorenzi said. “It’s just a matter of how much money are those three owners going to get.”

The department began plant salvaging and tortoise fencing in January, a $1.5 million project that should be completed soon.

Lorenzi said more than 20,000 endangered species plants that are being harvested in a nursery off U.S. 95. They will be replanted during the frontage road construction that will go from Foothill to Railroad Pass.

MOST READ
LISTEN TO THE TOP FIVE HERE
THE LATEST
Feds take over Sylvanie case

The case against Boulder City’s Terry Sylvanie took a turn last month when a federal grand jury indicted him on charges of distributing and possessing child sexual abuse images.

CCSD receives more input on master plan

More than 50 parents, educators and interested residents met for round two of discussion regarding Clark County School District’s preliminary draft options for its Facility Master Plan.

Jammin’ at the Jamboree

A member of the Flippenout Trampoline team appears to be walking on air, much to the delight of the crowd.

Eagles finish league play undefeated

Looking to reclaim the 3A state title, Boulder City High School boys volleyball completed their first step, finishing league play with an undefeated record after beating rival Moapa Valley 3-1 on April 29.

Track teams head to regionals Friday

Hosting a small-school invitational on May 1, Boulder City High School girls track and field finished second out of 13 programs, while the boys finished sixth out of 13 schools.

Softball ends regular season by defeating Moapa Valley

Rising to the occasion, Boulder City High School softball defeated rival Moapa Valley 7-3 April 30 to finish the regular season on a high note.

BCHS band performs in Disneyland

There are performances, and then there are moments that become part of the magic.