68°F
weather icon Clear

Ready (almost) to roll: Construction of I-11 to be finished by end of year

For nearly three years, large pieces of construction equipment have dotted the landscape around Boulder City as work has progressed on the building of Interstate 11.

With the arrival of 2018, crews are on pace to have the project completed before the end of the year.

The Nevada Department of Transportation and the Regional Transportation Commission of Southern Nevada have been working simultaneously to build the first two phases of the interstate highway, which will eventually connect Las Vegas to Phoenix.

NDOT’s 2.5-mile section, which covers the area from Railroad Pass to U.S. Highway 95, is set for “contractual completion” in April, according to project manager Ryan Wheeler, and traffic is expected to be moved to new alignments before that.

“Overall, given the circumstances, it has gone as smoothly as possible,” Wheeler said. “We are excited to get it open to the motorists.”

Monika Bertaki, spokesperson for the RTC, said it is scheduled to complete its 12.5-mile stretch from the intersection with U.S. 95 to U.S. Highway 93 near the Hoover Dam Bypass Bridge in October, when it will open to traffic.

According to Wheeler, the contractual completion date — when all details have been finalized and signed off on — has been moved to April, but he expects the majority of the work to be finished by mid-February.

That will allow the agencies to shift traffic from northbound U.S. 93 onto the interstate heading toward Henderson, as well as opening the new Railroad Pass interchange, Wheeler said.

“The new 95-I-11 interchange will be open before May,” he said. “Once Phase 1 is complete, if you want to go onto southbound 95, you won’t have to divert. You can take I-11.”

Plans have been adjusted continually throughout the project to accommodate issues that have caused delays.

Joe DeSimone, owner of the Railroad Pass Casino, had expected the land in front of the casino that is now being used for a portion of U.S. 93/95 to be returned to him before the end of 2017.

Though Wheeler commended Fisher Sand and Gravel for its work, any construction project will inevitably run across challenges that delay completion. One of the biggest challenges was relocating utilities, he said.

Bertaki said the RTC and its primary contractor, Las Vegas Paving, haven’t encountered any issues that have caused delays.

Before Phase 2 opens, “the contractor will go through punch-list items for quality assurance and then review or modify any items prior to completion,” she said.

Ground was broken for the four-lane interstate in April 2015 during a ceremony attended by numerous local, state and national officials. The highway will include interchanges at U.S. Highways 95 and 93, 10 bridges, four wildlife undercrossings, one wildlife overcrossing, an off-highway vehicle crossing and a scenic parking area overlooking Lake Mead.

Overall, the project will cost $318 million, with $249.2 million coming from federal funds.

Wheeler said an official opening ceremony will likely be held in October when both phases are complete.

The project has created hundreds of jobs.

Tony Illia, public information officer for NDOT, said there are currently 60 workers on-site, but there have been as many as 200 during the peak of construction activity.

Bertaki said there are currently 90 construction employees working on Phase 2.

“The number of employees can vary day by day due to the different aspects of the project. Thus far, there have been 1,078 construction employees on the project.”

Hali Bernstein Saylor is editor of the Boulder City Review. She can be reached at hsaylor@bouldercityreview.com or at 702-586-9523. Follow @HalisComment on Twitter.

MOST READ
LISTEN TO THE TOP FIVE HERE
THE LATEST
Spring Jamboree features something for everyone

If one is looking for an event that checks just about every box to have a fun weekend in Boulder City, the annual Spring Jamboree is just that.

Track teams shine at home meet as girls dominate

Continuing to excel in weekday events, both Boulder City High School track and field programs shined on their home turf.

Private helipad is becoming closer to reality

A request to build a private residential heliport cleared a second hurdle last week during more than an hour-long presentation and discussion.

Longtime resident turning 100

The number of Americans who are 100 years or older is expected to hit 101,000 this year.

Baseball knocks off 5A foe Coronado

Playing inspiring baseball, Boulder City High School knocked off 5A Coronado 10-8 on April 16, while just falling to 5A Basic 12-11 on April 18.

Library gearing up for summer

This May we have some wonderful programs coming to the library, including the kickoff to the much-anticipated 2026 Summer Reading Program.

Clean, clean Boulder City

Saturday, volunteers got a 7 a.m. start for Shine Boulder City, hosted by Main Street Boulder City. The clean-up was an initiative through American 250 Nevada. Volunteers helped clean statues, benches and some business exteriors within the Historic Downtown District.

A weekend of art

This past weekend, the Boulder City Art Guild hosted its annual Artists in Action show and sale at the Boulder City Parks and Rec gym. While members do not have to live in Boulder City, all participants must be members of the Art Guild. Top, Boulder City artist Barbara Pearce uses a dotting technique to paint images onto rocks. Below, Ernie Valdovinos sculpts a rabbit from clay.

A busy spring at Mitchell

As always, the leaders at Mitchell have been busy.