54°F
weather icon Clear

Ready (almost) to roll: Construction of I-11 to be finished by end of year

For nearly three years, large pieces of construction equipment have dotted the landscape around Boulder City as work has progressed on the building of Interstate 11.

With the arrival of 2018, crews are on pace to have the project completed before the end of the year.

The Nevada Department of Transportation and the Regional Transportation Commission of Southern Nevada have been working simultaneously to build the first two phases of the interstate highway, which will eventually connect Las Vegas to Phoenix.

NDOT’s 2.5-mile section, which covers the area from Railroad Pass to U.S. Highway 95, is set for “contractual completion” in April, according to project manager Ryan Wheeler, and traffic is expected to be moved to new alignments before that.

“Overall, given the circumstances, it has gone as smoothly as possible,” Wheeler said. “We are excited to get it open to the motorists.”

Monika Bertaki, spokesperson for the RTC, said it is scheduled to complete its 12.5-mile stretch from the intersection with U.S. 95 to U.S. Highway 93 near the Hoover Dam Bypass Bridge in October, when it will open to traffic.

According to Wheeler, the contractual completion date — when all details have been finalized and signed off on — has been moved to April, but he expects the majority of the work to be finished by mid-February.

That will allow the agencies to shift traffic from northbound U.S. 93 onto the interstate heading toward Henderson, as well as opening the new Railroad Pass interchange, Wheeler said.

“The new 95-I-11 interchange will be open before May,” he said. “Once Phase 1 is complete, if you want to go onto southbound 95, you won’t have to divert. You can take I-11.”

Plans have been adjusted continually throughout the project to accommodate issues that have caused delays.

Joe DeSimone, owner of the Railroad Pass Casino, had expected the land in front of the casino that is now being used for a portion of U.S. 93/95 to be returned to him before the end of 2017.

Though Wheeler commended Fisher Sand and Gravel for its work, any construction project will inevitably run across challenges that delay completion. One of the biggest challenges was relocating utilities, he said.

Bertaki said the RTC and its primary contractor, Las Vegas Paving, haven’t encountered any issues that have caused delays.

Before Phase 2 opens, “the contractor will go through punch-list items for quality assurance and then review or modify any items prior to completion,” she said.

Ground was broken for the four-lane interstate in April 2015 during a ceremony attended by numerous local, state and national officials. The highway will include interchanges at U.S. Highways 95 and 93, 10 bridges, four wildlife undercrossings, one wildlife overcrossing, an off-highway vehicle crossing and a scenic parking area overlooking Lake Mead.

Overall, the project will cost $318 million, with $249.2 million coming from federal funds.

Wheeler said an official opening ceremony will likely be held in October when both phases are complete.

The project has created hundreds of jobs.

Tony Illia, public information officer for NDOT, said there are currently 60 workers on-site, but there have been as many as 200 during the peak of construction activity.

Bertaki said there are currently 90 construction employees working on Phase 2.

“The number of employees can vary day by day due to the different aspects of the project. Thus far, there have been 1,078 construction employees on the project.”

Hali Bernstein Saylor is editor of the Boulder City Review. She can be reached at hsaylor@bouldercityreview.com or at 702-586-9523. Follow @HalisComment on Twitter.

MOST READ
LISTEN TO THE TOP FIVE HERE
THE LATEST
Council nixes Medo’s monster (truck) idea

There was a lot of talking around the issue and trying to be diplomatic. For a while. But, while the discussion centered around the appropriate use of land, in truth the discussion was likely over with the first mention of the term, “monster truck.”

Railroad museum set for spring completion

Construction on the Nevada State Railroad Museum at the busiest intersection in town is progressing at a rapid pace and because of that, is set for a spring completion.

Irrigation project turns off… for now

Readers whose attention span has not been destroyed by TikTok and general social media use may recall that when city council went on for more than an hour talking about where to allow off-leash dog “recreation” options, one of the sticking points was Wilbur Square

Kicking off the season

Photos by Ron Eland/Boulder City Review

Leash law is in effect

After an almost four-year saga, the part of Boulder City code that allowed dog owners to have their dogs off-leash in public as long as they were under verbal control practically (though not officially) goes away as of Dec. 4.

Historic designation sought for hangar

Getting the old Bullock Field Navy Hangar onto the National Registry of Historic Places has been on the radar of the Boulder City Historic Preservation Commission for about a year and a half and earlier this month, the city council agreed.

Council votes to reverse decision on historic home

Earlier this year, the city council voted to reverse a planning commission decision. It was not of note because no one in the ranks of city staff could remember such a reversal ever having happened in the time they worked for the city.

That year Santa, Clydesdales came to BC

Many local residents remember in 2019 when the world-famous Budweiser Clydesdales made an appearance in Boulder City in the former Vons parking lot.

Spreading joy for the holidays

The name may have changed but the dedication and work that goes into it has not changed.