107°F
weather icon Windy

Leaky part delays transformer installation

A faulty part has delayed the installation of Boulder City’s new backup transformer by one year.

A leak in the new transformer was discovered in July, four months after its arrival, and staff contacted the manufacturer, according to Lisa LaPlante, the city’s communications manager.

“One of the manufactured parts needed to be replaced with a new manufactured part, which took several weeks to complete,” she said. “Once the manufacturer received the part, the city was notified the part was incorrect and another one had to be manufactured.”

The new part was installed in January. Staff tested it to ensure it does not leak and the part passed inspection, LaPlante said. Until the transformer was complete and ready to use, the city held on to part of the payment to the manufacturer, Virginia Transformer.

The new transformer, which costs $1.1 million and weighs about 109 tons, will increase the reliability of the city’s electrical system.

“The next step is to complete the bid package for the above-grade construction portion of the project,” LaPlante said. “We are currently completing our 100 percent plans and specifications review and plan to advertise for construction this spring. ”

The new backup transformer is now expected to be operational in October. The delay has not caused an increase in cost.

Though the transformer, which will serve as the backup to the main electrical system, is ready for the next step for installation, the city has chosen to delay the process to get through the hot summer months.

If the existing transformer is disconnected from the Western Area Power Administration and there were any issues installing the new transformer, the city would be left without any backup to its power-supplying system.

In addition to the transformer, the city will be installing a new circuit breaker and other items for the system, which were purchased earlier.

“City staff has determined that starting phase 2 of the project now, this close to summer, is needlessly risky. … The better course of action is to continue to rely on the old transformer for backup power this summer and to commence breaker replacement starting in October 2019,” LaPlante said.

In 2017, then-Public Works Director Scott Hansen said the process to replace the more than 50-year-old transformer would not affect daily service for the city’s electrical customers. It would, however, be critical to serve the community should there be a problem with the city’s primary power source at the Mead Substation.

When the new transformer was delivered in April 2018, Rory Dwyer, who was the city’s electric utility administrator, said the existing backup does not have the capacity to deliver the large amount of energy needed during the summer.

According to LaPlante, the city holds a five-year warranty on the new transformer, which began now that the final payment has been released.

Contact reporter Celia Shortt Goodyear at cgoodyear@bouldercityreview.com or at 702-586-9401. Follow her on Twitter @csgoodyear.

THE LATEST
Planning Commission denies church housing project

Despite agreeing that there is a need in town for affordable senior housing, the majority of those on the Boulder City Planning Commission did not feel the location of a proposed multi-family complex was appropriate based upon current zoning and a previous agreement.

Unpacking the golf course deturfing issue

When the Boulder City Municipal Golf Course opened in 1973, it was a kind of golden age for golf as a suburban pastime.

Fancier permits now available through city

The long-contentious issue of allowing people to get a permit to keep more than three dogs and cats in their homes came to an end as the permit process opened up this week.

Pricey perks for favored CCSD administrators

Outgoing Superintendent Jesus Jara gave his top officials millions of dollars in additional benefits while keeping the information from elected school board trustees.

Public track discussion comes up at PR meeting

During public discussion at Monday’s Boulder City Parks and Recreation Commission meeting, a local couple brought up a topic that has not come up in the past. That being the constructing of a public track.

Not a pint-sized decision

Monday, the Boulder Dam Brewing Company posted something on Facebook that was unlike their normal posts about a new seasonal beer, upcoming band or their popular game nights. It was something they hoped they would never have to announce – their closure.

Turf reduction sees pushback

The second public meeting regarding the proposed reduction in turf at the Boulder City Municipal Golf Course was envisioned as the kind of input-lite that the first meeting back in April was. But the packed room at the Elaine K. Smith Building on Monday wasn’t having it.

Chamber event hosts members, special guest

When Boulder City Chamber of Commerce CEO Jill Rowland Lagan was introducing videos from those speaking on behalf of the chamber, few expected to see a former president doing so.

Dollar Tree closer to opening

If there was any doubt that the former 99 Cents Only Store in Boulder City would soon become a Dollar Tree, recently-placed signs should answer that question.