50°F
weather icon Mostly Cloudy

Leaky part delays transformer installation

A faulty part has delayed the installation of Boulder City’s new backup transformer by one year.

A leak in the new transformer was discovered in July, four months after its arrival, and staff contacted the manufacturer, according to Lisa LaPlante, the city’s communications manager.

“One of the manufactured parts needed to be replaced with a new manufactured part, which took several weeks to complete,” she said. “Once the manufacturer received the part, the city was notified the part was incorrect and another one had to be manufactured.”

The new part was installed in January. Staff tested it to ensure it does not leak and the part passed inspection, LaPlante said. Until the transformer was complete and ready to use, the city held on to part of the payment to the manufacturer, Virginia Transformer.

The new transformer, which costs $1.1 million and weighs about 109 tons, will increase the reliability of the city’s electrical system.

“The next step is to complete the bid package for the above-grade construction portion of the project,” LaPlante said. “We are currently completing our 100 percent plans and specifications review and plan to advertise for construction this spring. ”

The new backup transformer is now expected to be operational in October. The delay has not caused an increase in cost.

Though the transformer, which will serve as the backup to the main electrical system, is ready for the next step for installation, the city has chosen to delay the process to get through the hot summer months.

If the existing transformer is disconnected from the Western Area Power Administration and there were any issues installing the new transformer, the city would be left without any backup to its power-supplying system.

In addition to the transformer, the city will be installing a new circuit breaker and other items for the system, which were purchased earlier.

“City staff has determined that starting phase 2 of the project now, this close to summer, is needlessly risky. … The better course of action is to continue to rely on the old transformer for backup power this summer and to commence breaker replacement starting in October 2019,” LaPlante said.

In 2017, then-Public Works Director Scott Hansen said the process to replace the more than 50-year-old transformer would not affect daily service for the city’s electrical customers. It would, however, be critical to serve the community should there be a problem with the city’s primary power source at the Mead Substation.

When the new transformer was delivered in April 2018, Rory Dwyer, who was the city’s electric utility administrator, said the existing backup does not have the capacity to deliver the large amount of energy needed during the summer.

According to LaPlante, the city holds a five-year warranty on the new transformer, which began now that the final payment has been released.

Contact reporter Celia Shortt Goodyear at cgoodyear@bouldercityreview.com or at 702-586-9401. Follow her on Twitter @csgoodyear.

Don't miss the big stories. Like us on Facebook.
THE LATEST
Salary range, guidelines set for new city attorney, manager

The search for the next city manager and city attorney is a little more defined as City Council recently approved the salary range and compensation package for each position.

Purpose of proposed ballot question contested

City Council is divided on whether safety or growth is the purpose of a proposed ballot question about airport capital improvement projects and have yet to decide about moving forward with it.

Three announce plans to seek council seat

Candidate filing for Boulder City’s 2021 municipal election starts in less than two weeks and three residents have already announced their intention to run for city office.

Temporary staff check for COVID compliance

Boulder City is using temporary part-time code enforcement officers to help ensure that local businesses are complying with current health and safety guidelines for the pandemic.

Two council seats up for election

The 2021 municipal election will see residents voting to fill two seats on City Council as well as offer guidance on some community issues.

Old pet cemetery to remain intact

A new solar project will not infringe on the local pet cemetery put in place years ago by a longtime Boulder City resident.

Nevada’s road fatalities rose in 2020

Now that 2020 has come to a close, transportation officials hope the Las Vegas Valley can leave the “worst year ever” in its rear-view mirror.

Police raise awareness of 3-foot bicycle law to motorists

Local law enforcement agencies joined to raise awareness of Nevada’s “3-foot rule” for motorists during an enforcement event Dec. 30 on a trio of Summerlin roads.