81°F
weather icon Clear

Leaky part delays transformer installation

A faulty part has delayed the installation of Boulder City’s new backup transformer by one year.

A leak in the new transformer was discovered in July, four months after its arrival, and staff contacted the manufacturer, according to Lisa LaPlante, the city’s communications manager.

“One of the manufactured parts needed to be replaced with a new manufactured part, which took several weeks to complete,” she said. “Once the manufacturer received the part, the city was notified the part was incorrect and another one had to be manufactured.”

The new part was installed in January. Staff tested it to ensure it does not leak and the part passed inspection, LaPlante said. Until the transformer was complete and ready to use, the city held on to part of the payment to the manufacturer, Virginia Transformer.

The new transformer, which costs $1.1 million and weighs about 109 tons, will increase the reliability of the city’s electrical system.

“The next step is to complete the bid package for the above-grade construction portion of the project,” LaPlante said. “We are currently completing our 100 percent plans and specifications review and plan to advertise for construction this spring. ”

The new backup transformer is now expected to be operational in October. The delay has not caused an increase in cost.

Though the transformer, which will serve as the backup to the main electrical system, is ready for the next step for installation, the city has chosen to delay the process to get through the hot summer months.

If the existing transformer is disconnected from the Western Area Power Administration and there were any issues installing the new transformer, the city would be left without any backup to its power-supplying system.

In addition to the transformer, the city will be installing a new circuit breaker and other items for the system, which were purchased earlier.

“City staff has determined that starting phase 2 of the project now, this close to summer, is needlessly risky. … The better course of action is to continue to rely on the old transformer for backup power this summer and to commence breaker replacement starting in October 2019,” LaPlante said.

In 2017, then-Public Works Director Scott Hansen said the process to replace the more than 50-year-old transformer would not affect daily service for the city’s electrical customers. It would, however, be critical to serve the community should there be a problem with the city’s primary power source at the Mead Substation.

When the new transformer was delivered in April 2018, Rory Dwyer, who was the city’s electric utility administrator, said the existing backup does not have the capacity to deliver the large amount of energy needed during the summer.

According to LaPlante, the city holds a five-year warranty on the new transformer, which began now that the final payment has been released.

Contact reporter Celia Shortt Goodyear at cgoodyear@bouldercityreview.com or at 702-586-9401. Follow her on Twitter @csgoodyear.

MOST READ
THE LATEST
Toll Brothers gets split decision

The development of the area near Boulder Creek Golf Course known as Tract 350 (the sale of which is slated to pay for the majority of the planned replacement for the aging municipal pool) may have hit a snag last week as the planning commission voted 5-1 to deny the developers’ request to build houses closer to the street than is allowed under current law.

Council gives nod to 185 new hangars

There is at least one part of Boulder City that is set to see growth in the coming years. A lot of growth.

Boulder City ready to celebrate America

Boulder City resident James Cracolici may have put it best when he called the annual July 4 Damboree, “The crown jewel of all events held in Boulder City.”

BC can ban backyard breeders

Although there is nothing on any city agenda yet, the resolution of the issue of whether pet breeding will be allowed in Boulder City took a huge step forward last week as Nevada Attorney General Aaron Ford released an official opinion on the intent and limitations of state law that had been requested by city staff last year.

Completion dates for two road projects pushed back

Mayor Joe Hardy tacitly acknowledged that Boulder City gets, perhaps, more than its fair share of funding from the Regional Transportation Commission, given the city’s size.

Businesses recognized at Chamber awards night

The Boulder City Chamber of Commerce’s annual installation and awards night featured many business owners in town and even had an appearance, albeit an A.I.-generated one, by Audrey Hepburn.

Parallel parking approved

Like so many other things in the world of Boulder City government, the issue of reconfiguring parking in the historic downtown area along Nevada Way, which generated enough heat to cause council members to delay a decision up until the last possible moment, ended with more of a whimper than a bang.

Ways to reduce summer power bills

Now that the thermometer is on the rise outdoors, the cost to cool homes and businesses on the inside is doing the same.