91°F
weather icon Clear

Hoover Dam marks 85th anniversary of final concrete pour

On Friday, May 29, Hoover Dam celebrates a unique anniversary. It will have been 85 years since the last of the concrete was poured for the project.

According to the Bureau of Reclamation, the dam alone contains 3.25 million cubic yards of concrete. Including the power plant, spillway tunnels and other equipment needed for it to operate, there are 4.36 million cubic yards of it at the structure.

“This was an incredible project,” said Mark Hall-Patton, administrator of the Clark County Museum. “It was the largest scale engineering project and yet they did it under time and under budget.”

To pour all that concrete, workers had to place approximately 160,000 cubic yards per month, and when it was finished, the project was still far from being complete.

“There was actually a fair amount (still) to do” said Hall-Patton. “This was a milestone everyone could understand.”

The concrete portion was the most visible part of Hoover Dam and was built from 215 concrete blocks put into columns. Once it was poured, the workers still had to set up the turbines, build headquarters, take down temporary structures and install everything needed to get the electrical systems going.

Work also had to be done to cool down and set the concrete so grout could be put in to keep all the blocks together.

“Concrete doesn’t set up immediately,” Hall-Patton said. “It takes decades.”

To speed that time frame up, more than 582 miles of 1-inch steel pipe were embedded into the dam so ice water could circulate through it. The cooling process was completed in March 1935, according to the Bureau of Reclamation.

“When you’re looking … at a project of that size, this was larger than any other project in the United States,” added Hall-Patton. “It was in the middle of the desert, during the Depression.”

Hoover Dam was built between 1931 and 1936 and helps provide water and hydro-electrical power to the West. Once all the concrete had been poured by May 29, 1935, the rest of the features were completed less than a year later on March 1, 1936. Contractor Six Companies Inc. had seven years from April 20, 1931, to complete the project, according to the Bureau of Reclamation. They completed it in five years, and their bid was approximately $24,000 less than the government’s estimated cost.

Contact reporter Celia Shortt Goodyear at cgoodyear@bouldercityreview.com or at 702-586-9401. Follow her on Twitter @csgoodyear.

MOST READ
LISTEN TO THE TOP FIVE HERE
THE LATEST
Feds take over Sylvanie case

The case against Boulder City’s Terry Sylvanie took a turn last month when a federal grand jury indicted him on charges of distributing and possessing child sexual abuse images.

CCSD receives more input on master plan

More than 50 parents, educators and interested residents met for round two of discussion regarding Clark County School District’s preliminary draft options for its Facility Master Plan.

Jammin’ at the Jamboree

A member of the Flippenout Trampoline team appears to be walking on air, much to the delight of the crowd.

Eagles finish league play undefeated

Looking to reclaim the 3A state title, Boulder City High School boys volleyball completed their first step, finishing league play with an undefeated record after beating rival Moapa Valley 3-1 on April 29.

Track teams head to regionals Friday

Hosting a small-school invitational on May 1, Boulder City High School girls track and field finished second out of 13 programs, while the boys finished sixth out of 13 schools.

Softball ends regular season by defeating Moapa Valley

Rising to the occasion, Boulder City High School softball defeated rival Moapa Valley 7-3 April 30 to finish the regular season on a high note.

BCHS band performs in Disneyland

There are performances, and then there are moments that become part of the magic.