87°F
weather icon Clear

Hoover Dam marks 85th anniversary of final concrete pour

On Friday, May 29, Hoover Dam celebrates a unique anniversary. It will have been 85 years since the last of the concrete was poured for the project.

According to the Bureau of Reclamation, the dam alone contains 3.25 million cubic yards of concrete. Including the power plant, spillway tunnels and other equipment needed for it to operate, there are 4.36 million cubic yards of it at the structure.

“This was an incredible project,” said Mark Hall-Patton, administrator of the Clark County Museum. “It was the largest scale engineering project and yet they did it under time and under budget.”

To pour all that concrete, workers had to place approximately 160,000 cubic yards per month, and when it was finished, the project was still far from being complete.

“There was actually a fair amount (still) to do” said Hall-Patton. “This was a milestone everyone could understand.”

The concrete portion was the most visible part of Hoover Dam and was built from 215 concrete blocks put into columns. Once it was poured, the workers still had to set up the turbines, build headquarters, take down temporary structures and install everything needed to get the electrical systems going.

Work also had to be done to cool down and set the concrete so grout could be put in to keep all the blocks together.

“Concrete doesn’t set up immediately,” Hall-Patton said. “It takes decades.”

To speed that time frame up, more than 582 miles of 1-inch steel pipe were embedded into the dam so ice water could circulate through it. The cooling process was completed in March 1935, according to the Bureau of Reclamation.

“When you’re looking … at a project of that size, this was larger than any other project in the United States,” added Hall-Patton. “It was in the middle of the desert, during the Depression.”

Hoover Dam was built between 1931 and 1936 and helps provide water and hydro-electrical power to the West. Once all the concrete had been poured by May 29, 1935, the rest of the features were completed less than a year later on March 1, 1936. Contractor Six Companies Inc. had seven years from April 20, 1931, to complete the project, according to the Bureau of Reclamation. They completed it in five years, and their bid was approximately $24,000 less than the government’s estimated cost.

Contact reporter Celia Shortt Goodyear at cgoodyear@bouldercityreview.com or at 702-586-9401. Follow her on Twitter @csgoodyear.

MOST READ
LISTEN TO THE TOP FIVE HERE
THE LATEST
Chamber of commerce honors its own

Think of it as the Academy Awards for Boulder City businesses.

See Spot Run lease with city is expected to be renewed

A bill was introduced last week by city council that gives those with dogs a second option to let them run free regardless of the time of day.

Fishing for free

Photos by Ron Eland/Boulder City Review

Eagles swimmers bring home postseason honors

Following a successful swim season, six Eagle boys swimmers and one girls swimmer represented Boulder City High School on the All-Southern Nevada team.

Aten named one of best

Finishing as 3A state champion runners-up, three Boulder City High School baseball players were selected to the All-Southern Nevada team, representing the top players in the state, regardless of classification.

A rad evening in downtown Boulder City

Saturday night, a large crowd donned their best 1980s attire, which included an abundance of neon-colored clothing as part of the aptly-named Neon Nights. The block party was hosted by Main Street Boulder City and served as a make-up event for their planned New Year’s Eve celebration, which was canceled due to impending weather. Attendees filled the restautants and bars along the steet, while listening to 80s music played by DJ Mike Pacini.

Golden Eagle Hall of Fame inductees named

For Boulder City High School athletes, it’s one of the biggest honors a former Eagle can get.

Unique art canvas

Photos by Ron Eland/Boulder City Review