54°F
weather icon Cloudy

Hoover Dam marks 85th anniversary of final concrete pour

On Friday, May 29, Hoover Dam celebrates a unique anniversary. It will have been 85 years since the last of the concrete was poured for the project.

According to the Bureau of Reclamation, the dam alone contains 3.25 million cubic yards of concrete. Including the power plant, spillway tunnels and other equipment needed for it to operate, there are 4.36 million cubic yards of it at the structure.

“This was an incredible project,” said Mark Hall-Patton, administrator of the Clark County Museum. “It was the largest scale engineering project and yet they did it under time and under budget.”

To pour all that concrete, workers had to place approximately 160,000 cubic yards per month, and when it was finished, the project was still far from being complete.

“There was actually a fair amount (still) to do” said Hall-Patton. “This was a milestone everyone could understand.”

The concrete portion was the most visible part of Hoover Dam and was built from 215 concrete blocks put into columns. Once it was poured, the workers still had to set up the turbines, build headquarters, take down temporary structures and install everything needed to get the electrical systems going.

Work also had to be done to cool down and set the concrete so grout could be put in to keep all the blocks together.

“Concrete doesn’t set up immediately,” Hall-Patton said. “It takes decades.”

To speed that time frame up, more than 582 miles of 1-inch steel pipe were embedded into the dam so ice water could circulate through it. The cooling process was completed in March 1935, according to the Bureau of Reclamation.

“When you’re looking … at a project of that size, this was larger than any other project in the United States,” added Hall-Patton. “It was in the middle of the desert, during the Depression.”

Hoover Dam was built between 1931 and 1936 and helps provide water and hydro-electrical power to the West. Once all the concrete had been poured by May 29, 1935, the rest of the features were completed less than a year later on March 1, 1936. Contractor Six Companies Inc. had seven years from April 20, 1931, to complete the project, according to the Bureau of Reclamation. They completed it in five years, and their bid was approximately $24,000 less than the government’s estimated cost.

Contact reporter Celia Shortt Goodyear at cgoodyear@bouldercityreview.com or at 702-586-9401. Follow her on Twitter @csgoodyear.

MOST READ
LISTEN TO THE TOP FIVE HERE
THE LATEST
Public invited to BC State of the City address

It’s almost that time of the year when Mayor Joe Hardy does a little of both looking back and ahead as part of his annual State of the City address.

Woman arrested in ride-share shooting

A woman faces six charges after an Uber driver says she shot at him.

Ring in the new year in downtown BC

It’s now less than a week away before people will be practicing their backward countdown from 10 to 1, while often wishing the year ahead will be better than the 365 days that just went by in a blink of an eye.

Four King students hit reading milestone

If one were to listen to William O’Shaughnessy, Kailaash Malacarne, Emma Graham and Maxwell O’Connor talk about reading, and the excitement that elicits, it shows that there’s hope that in a digital-based world, book stores and libraries will be around for many years to come.

Dump fees set to increase in 2026

Success or failure as a local politician is rarely about big flashy issues.

Council to take another look at second station

Boulder City Councilman Steve Walton has a soft spot for fire departments, especially the local one.