67°F
weather icon Mostly Clear

Hoover Dam marks 85th anniversary of final concrete pour

On Friday, May 29, Hoover Dam celebrates a unique anniversary. It will have been 85 years since the last of the concrete was poured for the project.

According to the Bureau of Reclamation, the dam alone contains 3.25 million cubic yards of concrete. Including the power plant, spillway tunnels and other equipment needed for it to operate, there are 4.36 million cubic yards of it at the structure.

“This was an incredible project,” said Mark Hall-Patton, administrator of the Clark County Museum. “It was the largest scale engineering project and yet they did it under time and under budget.”

To pour all that concrete, workers had to place approximately 160,000 cubic yards per month, and when it was finished, the project was still far from being complete.

“There was actually a fair amount (still) to do” said Hall-Patton. “This was a milestone everyone could understand.”

The concrete portion was the most visible part of Hoover Dam and was built from 215 concrete blocks put into columns. Once it was poured, the workers still had to set up the turbines, build headquarters, take down temporary structures and install everything needed to get the electrical systems going.

Work also had to be done to cool down and set the concrete so grout could be put in to keep all the blocks together.

“Concrete doesn’t set up immediately,” Hall-Patton said. “It takes decades.”

To speed that time frame up, more than 582 miles of 1-inch steel pipe were embedded into the dam so ice water could circulate through it. The cooling process was completed in March 1935, according to the Bureau of Reclamation.

“When you’re looking … at a project of that size, this was larger than any other project in the United States,” added Hall-Patton. “It was in the middle of the desert, during the Depression.”

Hoover Dam was built between 1931 and 1936 and helps provide water and hydro-electrical power to the West. Once all the concrete had been poured by May 29, 1935, the rest of the features were completed less than a year later on March 1, 1936. Contractor Six Companies Inc. had seven years from April 20, 1931, to complete the project, according to the Bureau of Reclamation. They completed it in five years, and their bid was approximately $24,000 less than the government’s estimated cost.

Contact reporter Celia Shortt Goodyear at cgoodyear@bouldercityreview.com or at 702-586-9401. Follow her on Twitter @csgoodyear.

MOST READ
LISTEN TO THE TOP FIVE HERE
THE LATEST
Truancy program deemed a big success

It’s an issue that plagues many schools – both big and small – these days. That being truancy.

A New Chapter Begins

Photos by Ron Eland/Boulder City Review

Zwahlen earns 3A player of the year

Helping guide Boulder City High School boys volleyball back to the 3A state title, senior David Zwahlen was named 3A player of the year.

Five Lady Eagles win awards

Helping Boulder City High School softball reach the postseason, five Eagles received postseason accolades.

Barbecue at its Best

Vehicles of all ages filled the park both days of the festival.

Woman found dead in Boulder City home was killed

The announcement came a day after the coroner’s office said a man who was also found dead in the house died from suicide. The Boulder City Police Department have not said publicly if the two deaths have been ruled a murder-suicide.

P.E. teacher hanging up whistle

For nearly 30 years, Donna Handley has taught the three R’s at Andrew J. Mitchell Elementary, but maybe not the three you may be thinking of – Running, Recreation and Respect.

More off-leash areas, times approved by council

By a rare 3-2 split, the Boulder City Council voted last week to give a few additional options for those residents who were opposed to the leash law passed late last year.