49°F
weather icon Mostly Cloudy

Hoover Dam marks 85th anniversary of final concrete pour

On Friday, May 29, Hoover Dam celebrates a unique anniversary. It will have been 85 years since the last of the concrete was poured for the project.

According to the Bureau of Reclamation, the dam alone contains 3.25 million cubic yards of concrete. Including the power plant, spillway tunnels and other equipment needed for it to operate, there are 4.36 million cubic yards of it at the structure.

“This was an incredible project,” said Mark Hall-Patton, administrator of the Clark County Museum. “It was the largest scale engineering project and yet they did it under time and under budget.”

To pour all that concrete, workers had to place approximately 160,000 cubic yards per month, and when it was finished, the project was still far from being complete.

“There was actually a fair amount (still) to do” said Hall-Patton. “This was a milestone everyone could understand.”

The concrete portion was the most visible part of Hoover Dam and was built from 215 concrete blocks put into columns. Once it was poured, the workers still had to set up the turbines, build headquarters, take down temporary structures and install everything needed to get the electrical systems going.

Work also had to be done to cool down and set the concrete so grout could be put in to keep all the blocks together.

“Concrete doesn’t set up immediately,” Hall-Patton said. “It takes decades.”

To speed that time frame up, more than 582 miles of 1-inch steel pipe were embedded into the dam so ice water could circulate through it. The cooling process was completed in March 1935, according to the Bureau of Reclamation.

“When you’re looking … at a project of that size, this was larger than any other project in the United States,” added Hall-Patton. “It was in the middle of the desert, during the Depression.”

Hoover Dam was built between 1931 and 1936 and helps provide water and hydro-electrical power to the West. Once all the concrete had been poured by May 29, 1935, the rest of the features were completed less than a year later on March 1, 1936. Contractor Six Companies Inc. had seven years from April 20, 1931, to complete the project, according to the Bureau of Reclamation. They completed it in five years, and their bid was approximately $24,000 less than the government’s estimated cost.

Contact reporter Celia Shortt Goodyear at cgoodyear@bouldercityreview.com or at 702-586-9401. Follow her on Twitter @csgoodyear.

MOST READ
LISTEN TO THE TOP FIVE HERE
THE LATEST
Dynamic duo lead Eagles basketball into playoffs

Ending the regular season on a high note with a 17-10 record, Boulder City High School boys basketball won their final two regular-season games.

Lady Eagles to host playoff game

Finishing the regular season on a high note, Boulder City High School girls basketball won their last two regular-season games, earning the right to host a home playoff game.

Eight wrestlers qualify for state tournament

Putting in work at Virgin Valley on Feb. 7, eight Boulder City High School wrestlers punched their ticket to state, highlighted by regional champions Coen Burrows and Otis Ruth.

Hardy, Walton to seek reelection; filing begins March 2

Even though the closing date to run for Boulder City Council and mayor is still more than a month away, there will be familiar faces in the race.

Woodbury honors Heart of the Community recipients

Last Saturday, some of our community’s most caring individuals were honored at Boulder City Hospital Foundation’s 14th annual Heart of the Community Gala, an event that raises essential funds to keep our non-profit Boulder City Hospital healthy and sustainable.

Lady Eagles drop a pair on the court

Currently sitting in fourth place in the 3A standings, Boulder City High School girls basketball dropped a pair of games this past week to Coral Academy and rival Virgin Valley.

Eagles split a pair of games this week

Splitting a pair of league games this past week, Boulder City High School boys basketball sits in third place in the 3A league standings.

Defense leads way on gridiron

Boulder City High School flag football advanced to 7-7 on the season after splitting a pair of games this past week.