59°F
weather icon Windy

Hoover Dam marks 85th anniversary of final concrete pour

On Friday, May 29, Hoover Dam celebrates a unique anniversary. It will have been 85 years since the last of the concrete was poured for the project.

According to the Bureau of Reclamation, the dam alone contains 3.25 million cubic yards of concrete. Including the power plant, spillway tunnels and other equipment needed for it to operate, there are 4.36 million cubic yards of it at the structure.

“This was an incredible project,” said Mark Hall-Patton, administrator of the Clark County Museum. “It was the largest scale engineering project and yet they did it under time and under budget.”

To pour all that concrete, workers had to place approximately 160,000 cubic yards per month, and when it was finished, the project was still far from being complete.

“There was actually a fair amount (still) to do” said Hall-Patton. “This was a milestone everyone could understand.”

The concrete portion was the most visible part of Hoover Dam and was built from 215 concrete blocks put into columns. Once it was poured, the workers still had to set up the turbines, build headquarters, take down temporary structures and install everything needed to get the electrical systems going.

Work also had to be done to cool down and set the concrete so grout could be put in to keep all the blocks together.

“Concrete doesn’t set up immediately,” Hall-Patton said. “It takes decades.”

To speed that time frame up, more than 582 miles of 1-inch steel pipe were embedded into the dam so ice water could circulate through it. The cooling process was completed in March 1935, according to the Bureau of Reclamation.

“When you’re looking … at a project of that size, this was larger than any other project in the United States,” added Hall-Patton. “It was in the middle of the desert, during the Depression.”

Hoover Dam was built between 1931 and 1936 and helps provide water and hydro-electrical power to the West. Once all the concrete had been poured by May 29, 1935, the rest of the features were completed less than a year later on March 1, 1936. Contractor Six Companies Inc. had seven years from April 20, 1931, to complete the project, according to the Bureau of Reclamation. They completed it in five years, and their bid was approximately $24,000 less than the government’s estimated cost.

Contact reporter Celia Shortt Goodyear at cgoodyear@bouldercityreview.com or at 702-586-9401. Follow her on Twitter @csgoodyear.

MOST READ
THE LATEST
A step back in time

If someone is researching Boulder City’s history, chances are the majority of what they find will center around the building of Hoover Dam.

Memorial deal gets approval from council

One of the final steps before installation of the monument honoring fallen soldier and Boulder City native Shane Patton happened without fanfare at the city council meeting this week.

Council OKs judge panel

If you didn’t read the agenda, you would have no idea that the city council took a vote on the issue of municipal judge in Boulder City.

Boulder City High robotics team to compete at UNLV

The High Scalers, the robotics team at Boulder City High School, will be competing in the Las Vegas Regionals of the FIRST Robotics Competition at the Thomas and Mack Center on the campus of UNLV this weekend.

Car show benefiting officers returns to BC

If you like car shows, food, music and being able to see celebrities from your youth, then mark Saturday, March 29 on your calendar.

Council nixes development idea

Call it fiscal creativity, although some developers prefer harsher terms.

Gaming in BC? Kinda…

There are only two cities in Nevada where gambling is illegal.

Garrett STEM certified by governor’s office

It’s been three years in the making but all that hard work paid off this past week for Garrett Junior High.