92°F
weather icon Clear

Cost estimates for Substation 3 soar by 141%

Rising costs continue to bedevil city plans for replacing and upgrading infrastructure. The latest example is related to efforts to upgrade Boulder City’s electric utility service as the cost estimates of Substation 3 soared by 141% and the scheduled completion date was pushed out by three full years.

“Substations are an integral part of the city’s electrical distribution infrastructure and take higher transmission voltage and transform it to a lower distribution voltage so it can be distributed and used throughout the community. Substations consist of transformers, breakers, feeders, structural components, a grounding system, a control house, and perimeter security access and controls,” explained Utilities Director Joe Stubitz.

“The city’s preliminary engineering cost estimate of $4.5 million for this project was derived from recent feeder upgrade projects which contain only one component of what makes up a substation. Due to this fact, the initial engineering estimates had a low degree of certainty until accurate pricing data could be gathered from the additional design and components needed. The first set of pricing data came back from the substation transformers which came in at over 100% of initial estimates, totaling over 80% of the initial estimated total project costs. With accurate pricing data and recent substation design and construction completion, the Colorado River Commission has developed new estimated project costs to complete the project. Lead times for the manufacturing of electrical equipment has also increased necessitating the scheduled completion date to be extended. The new estimated project costs for the complete rebuild of substation 3 is now $10,850,000 with a completion date of March 1, 2028. The rebuild of this substation is an integral part of the city’s distribution voltage conversion from 4 kV to 12 1/2 kV and will take all the loads of the existing substation, along with the existing loads at substation 2, which is at the intersection of Adams and Avenue B. The total costs to complete this project are within the existing utility rate study and do not currently impact utility rates.”

There is a lot to unpack in Stubitz’s explanation.

Under questioning from Councilwoman Cokie Booth, Stubitz explained that the initial cost estimate came from comparison with a feeder extension project. Crucially, a feeder extension does not include transformers, which are the most expensive part of a substation. (Transmission lines such as the ones that emanate from Hoover Dam carry electricity at very high voltages —generally higher than 69,000 volts or 69 kilo Volts. Distribution lines carry much lower voltage to end users after the voltage has been stepped down via a series of transformers.)

Stubitz said that when costs for the project were put together, it was with the assumption that each transformer would cost about $1 million. But when actual pricing came back, the transformers were closer to $2 million each. Substation 3 will, once completed, utilize two transformers.

“We go through the government agency so that we get a better price than if we just went out for an RFP,” Stubitz said in response to a question from Booth about the process. “We are in this interlocal agreement with the Colorado River Commission and they go out and do an RFP (request for proposal). So we have contracted with the state of Nevada and the Colorado River Commission since this is the work that they do frequently. They’re doing this work for other agencies so we utilize their expertise and their efforts to go out and solicit the vendors and the design. So they went out did an RFP through the Colorado River Commission. We did get a low bid back from that and I believe the total costs were around $3.8 million for the two substation transformers.”

Most questioning by council fell under the heading of (to quote Councilman Steve Walton in a meeting last year) “not asking a question you don’t already know the answer to.” They gave council members and Stubitz a chance to explain on the public record the importance of the substation upgrades and potential benefit to Boulder City residents and businesses.

The bottom line is capacity and reliability. Tripling the voltage of city distribution lines from 4 to 12 kV means the utility can push out more power to meet increasing demand and should, at least theoretically, reduce the number of unplanned electrical outages.

And city ratepayers are not out of the woods quite yet in terms of costs and potential effects on utility rates. Keep in mind that in a council meeting late last year, the council approved a one-word change to city code, changing the word “adjusted” to “increased.” The result of that change is that, at least unless that wording is changed at a later date, electricity rates in Boulder City can go up when prices the utility pays for power go up, but they cannot go down if costs for power drop. This was sold as a way to ensure that the utility has funds to pay for these planned upgrades.

Also, while Stubitz said that the increased costs of this upgrade would not impact current rates, he also referred to the current rate study used to set those rates. But he also noted that a new rate study would need to be done starting with the 2027 fiscal year, which begins on July 1, 2026. No guarantees have been made that rates will not increase at that time.

Still, even if rates do increase, as was pointed out by multiple members of the council, Boulder City still pays less for electricity than any other municipality in the state.

Originally scheduled for electrification in June of 2025, the completion date for Substation 3 has been pushed out to June of 2028 as lead times for procuring parts and equipment continue to increase along with prices.

MOST READ
LISTEN TO THE TOP FIVE HERE
THE LATEST
Boulder City woman scammed out of $250K

Imagine being the victim of fraud that nearly drained your life savings. But instead of that money being stolen by a thief or online scam artist, it was at the hands of a trusted friend.

NDW invites all to learn more about bighorn

For several years now, the Nevada Department of Wildlife has been on hand at Hemenway Park in the summer to answer questions and talk about Boulder City’s unofficial mascots.

Police blotter

More fun at the Backstop

BC swimmers part of history

Last Thursday, dozens of Boulder City kids participated in the World’s Largest Swimming Lesson, which is held worldwide with more than 400,000 participants in 56 countries. Boulder City has participated in this event for several years.

City, owners differ on motel district

The potential creation of a historic motel district for eight properties in town hit a roadblock last week. The potential project went from the front of the Boulder City Historic Preservation Commission’s stove to the back burner, at least for now.

The Nevada manufacturer behind every crewed NASA mission since 1968

More than half a century after its founding, the family-owned company remains distinctly American. Its pens are manufactured in Boulder City, displayed in New York’s Museum of Modern Art as examples of industrial design and have appeared in pop culture, including the “Seinfeld” episode “The Pen.”

National designation sought for hangar

It’s a small piece of Boulder City history that while out of sight, isn’t necessarily out of mind.

Henderson mulls data center pause

As cities and counties consider moratoriums, the stage is now set for a larger battle in Carson City.

3-sport standout Jenas-Keogh named Athlete of the Year

Excelling as a three-sport athlete, Boulder City High School senior Sancha Jenas-Keogh has been named Boulder City Review female athlete of the year.

Zwahlen earns BCR’s top athlete award

Called a generational talent by his head coach, Boulder City High School senior boys volleyball star David Zwahlen has been named Boulder City Review male athlete of the year.