Solar farm fined nearly $220K for air quality violations

A Boulder City solar farm construction site has racked up hundreds of thousands of dollars in fines this year for air quality violations, according to Clark County regulators.

Since April, the county has fined Rosendin Electric nearly $220,000 for failing to control dust during construction of a roughly 1,000-acre solar farm on U.S. Highway 95 near Interstate 11. In all but one of the eight instances, Rosendin has not contested the fines.

The county says the company is putting its business interests ahead of complying with air-quality standards.

“Well, from our perspective, they responded by continuing to be out of compliance and making business decisions that are based on how quickly they can get the project done, as opposed to implementing the best practices that are required in our air quality regulations,” said Marci Henson, director of Clark County’s department of environment and sustainability.

Those dust control efforts include keeping the ground wet to prevent dust from blowing away.

The county is capped at issuing a fine of $10,000 per day, per incident, she said.

“There’s not a lot of projects that can bleed $10,000 per day, per incident,” she said. “Because of the scale of this project, it’s so big and they’re going to be selling renewable energy, which is a hot commodity right now, it appears that they’ve made the business decision to do that.”

Henson said her department estimates anywhere from 40 tons to 70 tons of excess dust has blown from the Townsite Solar Garden project.

Dust clouds can cause breathing issues and are particularly challenging for people with existing respiratory conditions, Henson said.

Company responds

“When I received dust complaints earlier this year, I made sure that they were reported and that there was follow-up from the appropriate authority, Clark County,” said Mayor Kiernan McManus.

“I understand and share the concerns of our residents with naturally occurring asbestos in our area. While the area of this project has not been identified as having a concentration of asbestos, it is important that these conditions are responded to,” he added.

During a July hearing with county regulators, Amy Sue Ambrose, environmental director for Rosendin, said the company was making its best effort to control dust on a challenging site, including spraying more than 20 million gallons of water at the site between early May and the end of June.

In a statement, the company said it has taken steps to ensure dust on the site is controlled.

“The health and safety of the residents in Clark County are extremely important to Rosendin, and we understand that proper dust control is crucial, particularly in a desert-living environment,” the company said. “Rosendin is dedicated to monitoring and managing dust control on the Townsite Solar project.”

The company said it uses multiple approaches to control dust clouds in the area.

To date, Rosendin has spent $3 million on dust control, including using six full-time employees to manage dust at the site, the company said.

“Our employees are members of this community, and we value the health and well-being of all members of the Clark County community,” the company said. “We have received fines for dust mitigation, and we remain committed to doing everything we can to control dust. Dust compliance is a top focus for Rosendin, and our overall compliance on this project site has been positive. Rosendin is committed to working with Clark County and addressing the concerns that the community has raised.”

Repeat offenders

Clark County regulators have substantiated 37 of the 49 complaints they have received about the project from the public.

“Can’t breathe from all the dust coming off the solar field!!!!!!,” one person wrote to the county on Sept. 15. “Someone needs to take care of this it happens way too often.”

The anonymous complaint said the dust blowing from the project is a problem every day.

In July, another anonymous complaint submitted to the county raised concerns about being unable to see or breathe due to dust blowing.

The most recent violations happened in September.

Last month, Boulder City Council members approved rezoning a patch of desert to allow for the expansion of the project, despite the planning commission’s recommendation to deny it.

A representative of the project told council members that dust control measures could be improved if that has been a problem.

McManus said he supported the expansion because dust typically isn’t a problem with solar farms and project officials told him they have taken steps to ensure the recent issues will not continue.

“With the news of these fines, I have again asked the City manager to work with Rosendin and Clark County officials to ensure that dust mitigation efforts are enhanced in the future,” he said.

‘Cost of doing business’

At the July hearing with the county, David Dean, a dust management program supervisor for the county, said the company has faced similar challenges with dust in the area, but the location of this project has garnered more attention.

He said the root of the problem is Rosendin’s construction plan and process. If the company wanted to correct the problem, it wouldn’t grade off more soil than it could control, he said.

“And that’s their business model. They have a set time limit to finish this in and they’re going to finish it,” Dean said. “And if it means get environmental issues or fines, then they’re going to do it, because it’s the cost of doing business.”

He said the company doesn’t want to change how it does business, so the problems will continue.

Rick Shaffer, division manager for Rosendin Renewable Energy Group, said at the hearing that it’s not the company’s business plan that has caused problems. It’s the rigid terms of the company’s contract, which could cost Rosendin nearly $150,000 per day if it were late, he said.

“We aren’t afforded, unfortunately, the luxury and the time to construct it in the manner that you are suggesting, which is the right way to do it, but we can’t because of our contract and our scheduling and our time,” he said.

A spokesman for the county’s department of environment and sustainability said officials are leaving all options on the table, including dust permit suspension if Rosendin continues to “neglect its duties” to control the dust and protect air quality.

Boulder City Review staff members Hali Bernstein Saylor and Celia Shortt Goodyear contributed to this report.

Contact Blake Apgar at bapgar@reviewjournal.com or 702-387-5298. Follow @blakeapgar on Twitter.

MOST READ
LISTEN TO THE TOP FIVE HERE
THE LATEST
Preservation Day: A step back in time

Dozens of people had an opportunity to journey back in time and get an inside look into Boulder City’s past as part of Saturday’s annual Historic Preservation Day.

Jenas-Keogh paces girls on track

Putting their best foot forward, Boulder City High School track and field will be well respected at the 3A state meet, qualifying 12 girls and nine boys after this past week’s regional meet.

McClarens lead swimmers to title

Continuing their illustrious pedigree of excellence, Boulder City High School boys and girls swimming each took home 3A regional championships this past weekend.

Eagles finish as top seed from south

Making a return trip to the state tournament, Boulder City High School baseball enters as the top seed out of the south.

Grace Christian Academy set to close after 26 years

For a little more than a quarter century, Grace Christian Academy has offered an alternative to elementary education in Boulder City. But as of the end of this month, its doors will be closed.

That’s good; no, that’s bad

Have you ever noticed how life can feel perfectly calm, and then suddenly everything hits at once? The calm before the storm is a real phenomenon in nature. The atmosphere often becomes extra still and quiet just before a raging storm breaks. And then, when it finally rains, it often pours, as the saying goes.

Garrett excels in classroom, field, stage

Garrett Junior High School has been very busy this quarter. Across campus, classrooms are wrapping up their final projects and concluding MAP testing to bring us into the final few days of the school year.

Something new is afloat in Boulder City

Last week, city staff took the Municipal Pool bubble down for the last time.

Data centers still a hot topic

It’s one of the most discussed topics around town these days: that being the proposed data center in Eldorado Valley, nearly three miles from the nearest residence in Boulder City.