49°F
weather icon Clear

Hoover Dam marks 85th anniversary of final concrete pour

On Friday, May 29, Hoover Dam celebrates a unique anniversary. It will have been 85 years since the last of the concrete was poured for the project.

According to the Bureau of Reclamation, the dam alone contains 3.25 million cubic yards of concrete. Including the power plant, spillway tunnels and other equipment needed for it to operate, there are 4.36 million cubic yards of it at the structure.

“This was an incredible project,” said Mark Hall-Patton, administrator of the Clark County Museum. “It was the largest scale engineering project and yet they did it under time and under budget.”

To pour all that concrete, workers had to place approximately 160,000 cubic yards per month, and when it was finished, the project was still far from being complete.

“There was actually a fair amount (still) to do” said Hall-Patton. “This was a milestone everyone could understand.”

The concrete portion was the most visible part of Hoover Dam and was built from 215 concrete blocks put into columns. Once it was poured, the workers still had to set up the turbines, build headquarters, take down temporary structures and install everything needed to get the electrical systems going.

Work also had to be done to cool down and set the concrete so grout could be put in to keep all the blocks together.

“Concrete doesn’t set up immediately,” Hall-Patton said. “It takes decades.”

To speed that time frame up, more than 582 miles of 1-inch steel pipe were embedded into the dam so ice water could circulate through it. The cooling process was completed in March 1935, according to the Bureau of Reclamation.

“When you’re looking … at a project of that size, this was larger than any other project in the United States,” added Hall-Patton. “It was in the middle of the desert, during the Depression.”

Hoover Dam was built between 1931 and 1936 and helps provide water and hydro-electrical power to the West. Once all the concrete had been poured by May 29, 1935, the rest of the features were completed less than a year later on March 1, 1936. Contractor Six Companies Inc. had seven years from April 20, 1931, to complete the project, according to the Bureau of Reclamation. They completed it in five years, and their bid was approximately $24,000 less than the government’s estimated cost.

Contact reporter Celia Shortt Goodyear at cgoodyear@bouldercityreview.com or at 702-586-9401. Follow her on Twitter @csgoodyear.

MOST READ
THE LATEST
Council directs staff to draft new leash law

Three hours into a meeting that started with an hour of public comment exorciating the city council for current regulations regarding pet breeding and off-leash dogs, members voted to tie one of those issues up.

Governor honors veterans at SNSVH

More than 100 invited guests, veterans and elected officials turned out to Monday’s Veterans Day ceremony at the Southern Nevada State Veterans Home.

3 to vie for city manager position

The process for choosing a permanent (hopefully, given recent history) city manager is about to take a big step forward as the city council will get a chance to publicly question three candidates in a special meeting on Thursday, Nov. 21.

Note to readers: BC Review office to close Nov. 22

After 15 years in the Boulder City Downtown Mall (Old Town Mall), the Boulder City Review will close its office effective Nov. 22.

A New Beginning

Photos by Ron Eland

Ashurst tops Fox for council seat

A contentious election year has come to a close in Boulder City as city council candidate Denise Ashurst has emerged victorious with a nearly 2-1 vote lead over sitting Councilman Matt Fox.

Animal lover launches anti-breeding petition

The issue of allowing and permitting the practice of commercial pet breeding in Boulder City has officially moved beyond the city limits.

City relaunching Airport Day

Not seen in 15 years, Airport Day is returning to the Boulder City Airport on Saturday, Nov. 9 from 10 a.m. until 2 p.m.