Ready (almost) to roll: Construction of I-11 to be finished by end of year

For nearly three years, large pieces of construction equipment have dotted the landscape around Boulder City as work has progressed on the building of Interstate 11.

With the arrival of 2018, crews are on pace to have the project completed before the end of the year.

The Nevada Department of Transportation and the Regional Transportation Commission of Southern Nevada have been working simultaneously to build the first two phases of the interstate highway, which will eventually connect Las Vegas to Phoenix.

NDOT’s 2.5-mile section, which covers the area from Railroad Pass to U.S. Highway 95, is set for “contractual completion” in April, according to project manager Ryan Wheeler, and traffic is expected to be moved to new alignments before that.

“Overall, given the circumstances, it has gone as smoothly as possible,” Wheeler said. “We are excited to get it open to the motorists.”

Monika Bertaki, spokesperson for the RTC, said it is scheduled to complete its 12.5-mile stretch from the intersection with U.S. 95 to U.S. Highway 93 near the Hoover Dam Bypass Bridge in October, when it will open to traffic.

According to Wheeler, the contractual completion date — when all details have been finalized and signed off on — has been moved to April, but he expects the majority of the work to be finished by mid-February.

That will allow the agencies to shift traffic from northbound U.S. 93 onto the interstate heading toward Henderson, as well as opening the new Railroad Pass interchange, Wheeler said.

“The new 95-I-11 interchange will be open before May,” he said. “Once Phase 1 is complete, if you want to go onto southbound 95, you won’t have to divert. You can take I-11.”

Plans have been adjusted continually throughout the project to accommodate issues that have caused delays.

Joe DeSimone, owner of the Railroad Pass Casino, had expected the land in front of the casino that is now being used for a portion of U.S. 93/95 to be returned to him before the end of 2017.

Though Wheeler commended Fisher Sand and Gravel for its work, any construction project will inevitably run across challenges that delay completion. One of the biggest challenges was relocating utilities, he said.

Bertaki said the RTC and its primary contractor, Las Vegas Paving, haven’t encountered any issues that have caused delays.

Before Phase 2 opens, “the contractor will go through punch-list items for quality assurance and then review or modify any items prior to completion,” she said.

Ground was broken for the four-lane interstate in April 2015 during a ceremony attended by numerous local, state and national officials. The highway will include interchanges at U.S. Highways 95 and 93, 10 bridges, four wildlife undercrossings, one wildlife overcrossing, an off-highway vehicle crossing and a scenic parking area overlooking Lake Mead.

Overall, the project will cost $318 million, with $249.2 million coming from federal funds.

Wheeler said an official opening ceremony will likely be held in October when both phases are complete.

The project has created hundreds of jobs.

Tony Illia, public information officer for NDOT, said there are currently 60 workers on-site, but there have been as many as 200 during the peak of construction activity.

Bertaki said there are currently 90 construction employees working on Phase 2.

“The number of employees can vary day by day due to the different aspects of the project. Thus far, there have been 1,078 construction employees on the project.”

Hali Bernstein Saylor is editor of the Boulder City Review. She can be reached at hsaylor@bouldercityreview.com or at 702-586-9523. Follow @HalisComment on Twitter.

MOST READ
LISTEN TO THE TOP FIVE HERE
THE LATEST
Toll Brothers gets split decision

The development of the area near Boulder Creek Golf Course known as Tract 350 (the sale of which is slated to pay for the majority of the planned replacement for the aging municipal pool) may have hit a snag last week as the planning commission voted 5-1 to deny the developers’ request to build houses closer to the street than is allowed under current law.

Council gives nod to 185 new hangars

There is at least one part of Boulder City that is set to see growth in the coming years. A lot of growth.

Boulder City ready to celebrate America

Boulder City resident James Cracolici may have put it best when he called the annual July 4 Damboree, “The crown jewel of all events held in Boulder City.”

BC can ban backyard breeders

Although there is nothing on any city agenda yet, the resolution of the issue of whether pet breeding will be allowed in Boulder City took a huge step forward last week as Nevada Attorney General Aaron Ford released an official opinion on the intent and limitations of state law that had been requested by city staff last year.

Completion dates for two road projects pushed back

Mayor Joe Hardy tacitly acknowledged that Boulder City gets, perhaps, more than its fair share of funding from the Regional Transportation Commission, given the city’s size.

Businesses recognized at Chamber awards night

The Boulder City Chamber of Commerce’s annual installation and awards night featured many business owners in town and even had an appearance, albeit an A.I.-generated one, by Audrey Hepburn.

Parallel parking approved

Like so many other things in the world of Boulder City government, the issue of reconfiguring parking in the historic downtown area along Nevada Way, which generated enough heat to cause council members to delay a decision up until the last possible moment, ended with more of a whimper than a bang.

Ways to reduce summer power bills

Now that the thermometer is on the rise outdoors, the cost to cool homes and businesses on the inside is doing the same.