Council proposes to delay power line project; budget to move allocated funds to reserves

After residents protested adding overhead lines as part of a project to update the aging electrical system, the City Council removed it from the 2017-2018 fiscal year budget to research other options at its budget workshop Tuesday morning.

Funds designated for the 69kV transmission loop will be moved the city’s long-term reserves and increase them by approximately $1.97 million.

The proposed 2017-2018 fiscal year budget is $71 million and includes $30.5 million in the general fund, $2.4 million for general fund capital projects, $31.9 million in the utility fund, and $9.9 million for utility funds capital projects.

The tentative general fund budget also incorporates an additional $844,887 in revenues from building permits and consolidated tax revenues, as well as $216,000 for professional consulting services in the utility fund.

The general fund portion is about 7 percent lower than the 2016 fiscal year budget of approximately $32.9 million.

Boulder City Mayor Rod Woodbury made the motion to remove the utility upgrade project from this year’s budget and said other options for the 69kV loop are being explored, including moving the lines, using underground lines, and working with NV Energy to utilize its power lines in the area.

“I don’t want the public … to think that the message is we stop that project,” he said. “I think we do need to move forward with it. We just need to determine what the best way to do that project is.”

Woodbury estimated that it will take about six months to set up anything with NV Energy. He also suggested moving forward with another project: mapping Boulder City’s utility system.

“Project funding for the 69kV project will continue to be held in reserves, as we anticipated using those reserves (fund balance) to pay for the projects,” said Boulder City Finance Director Hyun Kim. “In its place the council authorized other projects, such as the utility (electrical) mapping and other distribution projects not to exceed $900,000. So of the $9 million plus in capital projects, we essentially brought that total utility capital improvement fund project down by $1.1 million. The additional fund balance (in excess of our 20 percent goal) would be held in long-term capital reserves.”

The city’s 20 percent goal equals approximately $6.74 million.

Long-term capital reserves for the utility fund are designated for infrastructure projects, especially those dealing with the aging electrical system. They can also be used for catastrophic events, like a substation failure.

“I think it’s wise to set aside that extra $2 million and not spend it down because we probably will need that either for the 69kV project or for some future project,” Woodbury said. “We’ve definitely got a lot on the horizon here.”

Councilman Duncan McCoy agreed with putting the project on hold and putting the money into the long-term reserves.

“I’ve been concerned for a long time what the city would do in case of a catastrophic failure in any of our utilities,” he said.

He added that most communities raise money quickly if that happens by floating some short-term debt and back that up with revenue bonds that are pledged against rate increases, but Boulder City can’t do that because its debt limit initiative.

“Two million won’t handle every catastrophic event … but at least it’s baby steps in the right direction,” Woodbury added.

The 69kV transmission loop project will add a second power line and increase electrical service reliability. Currently, the proposed route will connect Substation 3 near Adams Boulevard and River Mountain Avenue with Substation 6. The power line will be all overhead steel electric poles, which will be approximately 300 feet apart and range from 60-80 feet high.

Since being announced, residents have raised concerns about how the overhead lines would affect their views of Lake Mead and property values in the area.

The final 2017-2018 fiscal year budget is expected to be presented and approved at the council’s meeting on May 23.

Contact reporter Celia Shortt Goodyear at cgoodyear@bouldercityreview.com or at 702-586-9401. Follow her on Twitter @csgoodyear.

MOST READ
LISTEN TO THE TOP FIVE HERE
THE LATEST
Eagles pick up two key wins

Building a winning streak before the postseason, Boulder City High School baseball picked up victories this past week over Laughlin and White Pine.

Visitor center still on track

For those who drive by the soon-to-be completed Nevada State Railroad Museum Visitor Center, it’s hard not to see something new with each passing.

Volleyball squad undefeated in league

Remaining atop the 3A standings, Boulder City High School boys volleyball won a pair of league games this past week to advance to 7-0 in league play.

Thomas looks back at first year

With just about any new job, especially within a municipality, there’s a learning curve as one gets to know the issues and the people.

Boulder City Ambassadors

Photos by Ron Eland/Boulder City Review

Elections with love

I was happy to see that Boulder City is going to have an election that provides time for both communicating as well as understanding. It is unresolved until Tuesday, Nov. 3, 2026. Choices for city council should never be ignored or hurried. Our duty as citizens is to objectively apply the best information we have to decide for whom to vote.

Residential Amnesty Program starts May 1

Imagine getting ready to sell your house, or worse yet, have a disaster in the home, only to find out an earlier renovation or remodel was not up to code? Modifications can bring a home sale to a grinding halt, or cause problems for insurance reimbursement. If you renovated or remodeled your home or accessory structure without getting a building permit first, here is your opportunity to get in compliance.