Leaky part delays transformer installation

A faulty part has delayed the installation of Boulder City’s new backup transformer by one year.

A leak in the new transformer was discovered in July, four months after its arrival, and staff contacted the manufacturer, according to Lisa LaPlante, the city’s communications manager.

“One of the manufactured parts needed to be replaced with a new manufactured part, which took several weeks to complete,” she said. “Once the manufacturer received the part, the city was notified the part was incorrect and another one had to be manufactured.”

The new part was installed in January. Staff tested it to ensure it does not leak and the part passed inspection, LaPlante said. Until the transformer was complete and ready to use, the city held on to part of the payment to the manufacturer, Virginia Transformer.

The new transformer, which costs $1.1 million and weighs about 109 tons, will increase the reliability of the city’s electrical system.

“The next step is to complete the bid package for the above-grade construction portion of the project,” LaPlante said. “We are currently completing our 100 percent plans and specifications review and plan to advertise for construction this spring. ”

The new backup transformer is now expected to be operational in October. The delay has not caused an increase in cost.

Though the transformer, which will serve as the backup to the main electrical system, is ready for the next step for installation, the city has chosen to delay the process to get through the hot summer months.

If the existing transformer is disconnected from the Western Area Power Administration and there were any issues installing the new transformer, the city would be left without any backup to its power-supplying system.

In addition to the transformer, the city will be installing a new circuit breaker and other items for the system, which were purchased earlier.

“City staff has determined that starting phase 2 of the project now, this close to summer, is needlessly risky. … The better course of action is to continue to rely on the old transformer for backup power this summer and to commence breaker replacement starting in October 2019,” LaPlante said.

In 2017, then-Public Works Director Scott Hansen said the process to replace the more than 50-year-old transformer would not affect daily service for the city’s electrical customers. It would, however, be critical to serve the community should there be a problem with the city’s primary power source at the Mead Substation.

When the new transformer was delivered in April 2018, Rory Dwyer, who was the city’s electric utility administrator, said the existing backup does not have the capacity to deliver the large amount of energy needed during the summer.

According to LaPlante, the city holds a five-year warranty on the new transformer, which began now that the final payment has been released.

Contact reporter Celia Shortt Goodyear at cgoodyear@bouldercityreview.com or at 702-586-9401. Follow her on Twitter @csgoodyear.

THE LATEST
A primer on ‘public comment’ in council meetings

There have been a number of contentious issues to come before the city council in the past year. Short-term rentals, incorrect communication about the Republican caucus, pet breeding permits, off-highway vehicles on city streets.

Airport tower project takes a step forward

Plans to add a control tower to the Boulder City Municipal Airport took another step forward last week as the comment period for the draft environmental assessment prepared for the city and the Federal Aviation Administration came to an end on May 2.

Tedder looks back on tenure

Despite being in Boulder City less than three years, Taylour Tedder said he will always have a place in his heart for the town he served as city manager.

Lady Eagles dominant in playoff victories

Opening up regional play with a pair of routs, Boulder City High School softball looks primed for a state tournament appearance.

Spring Jamboree this weekend

It’s become one of the most popular annual events in Boulder City and this year is expected to be no different.

Off-road to go on-road?

“They didn’t want the apple, but do they want the orange?” asked Councilmember Sherri Jorgensen. “We’re still talking about fruit here.”

O’Shaughnessy records perfect ACT score

On Feb. 27, BCHS junior Sam O’Shaughnessy walked into the testing room to take the American College Test (better known as the ACT), hoping for a good score. Little did he know he’d walk out having done something just 3,000 students achieve each year – perfection.

Staff advises adding new full-time employees

The Boulder City governmental budget moved a couple of steps closer to its legally-mandated approval at the end of May as the city council heard revised revenue estimates and got requested additional information on a total of eight proposed new positions within the city.

What’s your sign?

In their 1971 hit entitled “Signs”, the 5 Man Electrical Band sang, “Sign, sign, everywhere a sign. Blockin’ out the scenery, breakin’ my mind. Do this, don’t do that, can’t you read the sign?”