Council proposes to delay power line project; budget to move allocated funds to reserves

After residents protested adding overhead lines as part of a project to update the aging electrical system, the City Council removed it from the 2017-2018 fiscal year budget to research other options at its budget workshop Tuesday morning.

Funds designated for the 69kV transmission loop will be moved the city’s long-term reserves and increase them by approximately $1.97 million.

The proposed 2017-2018 fiscal year budget is $71 million and includes $30.5 million in the general fund, $2.4 million for general fund capital projects, $31.9 million in the utility fund, and $9.9 million for utility funds capital projects.

The tentative general fund budget also incorporates an additional $844,887 in revenues from building permits and consolidated tax revenues, as well as $216,000 for professional consulting services in the utility fund.

The general fund portion is about 7 percent lower than the 2016 fiscal year budget of approximately $32.9 million.

Boulder City Mayor Rod Woodbury made the motion to remove the utility upgrade project from this year’s budget and said other options for the 69kV loop are being explored, including moving the lines, using underground lines, and working with NV Energy to utilize its power lines in the area.

“I don’t want the public … to think that the message is we stop that project,” he said. “I think we do need to move forward with it. We just need to determine what the best way to do that project is.”

Woodbury estimated that it will take about six months to set up anything with NV Energy. He also suggested moving forward with another project: mapping Boulder City’s utility system.

“Project funding for the 69kV project will continue to be held in reserves, as we anticipated using those reserves (fund balance) to pay for the projects,” said Boulder City Finance Director Hyun Kim. “In its place the council authorized other projects, such as the utility (electrical) mapping and other distribution projects not to exceed $900,000. So of the $9 million plus in capital projects, we essentially brought that total utility capital improvement fund project down by $1.1 million. The additional fund balance (in excess of our 20 percent goal) would be held in long-term capital reserves.”

The city’s 20 percent goal equals approximately $6.74 million.

Long-term capital reserves for the utility fund are designated for infrastructure projects, especially those dealing with the aging electrical system. They can also be used for catastrophic events, like a substation failure.

“I think it’s wise to set aside that extra $2 million and not spend it down because we probably will need that either for the 69kV project or for some future project,” Woodbury said. “We’ve definitely got a lot on the horizon here.”

Councilman Duncan McCoy agreed with putting the project on hold and putting the money into the long-term reserves.

“I’ve been concerned for a long time what the city would do in case of a catastrophic failure in any of our utilities,” he said.

He added that most communities raise money quickly if that happens by floating some short-term debt and back that up with revenue bonds that are pledged against rate increases, but Boulder City can’t do that because its debt limit initiative.

“Two million won’t handle every catastrophic event … but at least it’s baby steps in the right direction,” Woodbury added.

The 69kV transmission loop project will add a second power line and increase electrical service reliability. Currently, the proposed route will connect Substation 3 near Adams Boulevard and River Mountain Avenue with Substation 6. The power line will be all overhead steel electric poles, which will be approximately 300 feet apart and range from 60-80 feet high.

Since being announced, residents have raised concerns about how the overhead lines would affect their views of Lake Mead and property values in the area.

The final 2017-2018 fiscal year budget is expected to be presented and approved at the council’s meeting on May 23.

Contact reporter Celia Shortt Goodyear at cgoodyear@bouldercityreview.com or at 702-586-9401. Follow her on Twitter @csgoodyear.

MOST READ
LISTEN TO THE TOP FIVE HERE
THE LATEST
City not moving forward with motel district

It appears that everyone is on the same page in that they want to see motels in Boulder City retain their historic charm.

BC family creates hydration supplement for kids

Like many parents of school-aged children, Boulder City’s Alex and Anabel Smith often find their weekends filled with youth activities and sports.

City proposes utility rate hike

Last week, the city of Boulder City announced a proposal to raise utility rates by 15% over the next three years.

Celebrating America with love

The USA is the longest standing democratic republic in the history of the world. Much history has passed since the country declared its independence from Great Britain, hasn’t it? Even the king of England celebrated our independence by visiting the United States of America in April of this year.

Local duo competes in high school rodeo finals

Representing Boulder City in the high school rodeo scene, Aiden Brown and Alyvia Madsen competed in the National High School Finals Rodeo (NHSFR) in Lincoln, Neb. from July 19-25.

Ho(t), ho(t), ho(t)

It was Christmas in July Saturday as those seeking a little holiday cheer filled the basement of the Masonic Temple. The Boulder City Community Club and the Boulder City History and Arts Foundation co-hosted the event, which included a visit from Santa and the Grinch and Christmas music by Patrick Mahoney and Maire Egan on fiddle. More than a dozen gift baskets were donated by local residents and merchants as raffle prizes, while the food was also free thanks to donations. Proceeds were split between to the two hosting organizations.

City proposes utility rate hike

Thursday afternoon, the city of Boulder City posted on its official Facebook page a legal notice announcing a proposal to raise utility rates by 15% over the next three years.

Loophole lets data center evade public’s scrutiny

The unusual Bureau of Land Management approval has turned a controversial data center fight in Southern Nevada on its head. Here’s what happens next.