It doesn’t make sense to build the second phase of the Interstate 11 loop without making sure the first phase is completed at the same time to connect.

The first phase of the I-11 loop, formerly known as the Boulder City Bypass, is in the early stages with road construction possibly beginning late this year and taking until nearly the year 2020.

However, with the Regional Transportation Commission of Southern Nevada telling the City Council last week that construction on the second phase could start next fall and finish in 2017, the construction timeline of the connecting phase by Railroad Pass would have to be pushed up.

“It would force us to finish phase one because you can’t have a phase two without that phase one,” said Tony Lorenzi, senior project manager for the Nevada Transportation Department. “It would force us to hurry up and finish our portion.”

Phase one is being overseen by the department and phase two is being administered by the Transportation Commission.

Funding of the $300 million second phase hinges on a proposed fuel-tax increase that needs the approval of the Clark County Commission. If approved, the Transportation Commission would take $700 million to $800 million in bonds that would be paid back with future tax revenue.

Nearly $230 million of that funding would go toward the I-11 loop second phase.

Phase one is the realignment of U.S. Highway 93/95 by Railroad Pass, which would include removing the stoplight in front of the casino. The stoplight can cause traffic back up toward Boulder City during Friday evenings and holiday weekends.

“The main benefit of phase one if the removal of that half-signal,” Lorenzi said. “It’s a very dangerous intersection, it’s a high-crash location.”

Phase one will pull the highway away from the casino, which will improve traffic flow especially for tractor-trailers.

Lorenzi said $32 million in construction of the connector from the Railroad Pass interchange to U.S. 95 where the loop would begin in the phase one plans could move to phase two.

“We’re meeting with the RTC to see how we can integrate phase one into phase two and get the whole (I-11) built,” he said.

The department also meets with the Federal Highway Administration, which is studying an I-11 corridor from Phoenix to Las Vegas.

According to Lorenzi, right-of-way acquisitions are nearly complete with the state attorney general’s office negotiating right-of-way acquisitions for the first phase, including the three-acre portion controlled by Jericho Heights, as well as land held by Railroad Pass Casino and K&L Dirt.

“Our goal is to settle it before it even goes to court,” Lorenzi said. The cost of acquisition, which was budgeted at $20 million to $30 million, could be nearly $60 million.

However, the state does not have to wait for the settlements to be complete before the project can begin road construction.

“We could build the project tomorrow,” Lorenzi said. “It’s just a matter of how much money are those three owners going to get.”

The department began plant salvaging and tortoise fencing in January, a $1.5 million project that should be completed soon.

Lorenzi said more than 20,000 endangered species plants that are being harvested in a nursery off U.S. 95. They will be replanted during the frontage road construction that will go from Foothill to Railroad Pass.

THE LATEST
The Eagle has landed

City crews help align the eagle at the new welcome sign Monday morning. The $75,000 sign, which is funded by the city, will not only welcome those coming to town but also honors the Boulder City High School Eagles.

Tract 350 sale approved

Whether it will be enough to fund the projected $40 million-plus pool complex the city would like to build is still — given the realities of the current inflationary economic environment — an open question.

City’s pet licensing proposal still in limbo

As the proposal to allow for a license for pet breeding, as well as the keeping of more animals than the three currently allowed by city code that came within inches of becoming law in March of this year, appears to be in some kind of limbo. After it was tabled, and has not yet been rescheduled to come back before the city council, a related case recently came before the municipal court.

Students learn the fine art of guitar making

Jimi Hendrix, considered by many to be the greatest guitarist ever, once said of his craft, “Sometimes you want to give up the guitar, you’ll hate the guitar. But if you stick with it, you’ll be rewarded.”