City unveils draft for renovated parkway; plan includes wider sidewalks, bike lanes

A small group of Boulder City residents gathered at the Elaine K. Smith Center on Jan. 11 to give suggestions about the city’s plans to renovate Nevada Highway.

The projected $10 million Boulder City Parkway complete street project will renovate the streets and sidewalks from Buchanan Boulevard to Gingerwood Street to make it safer and more aesthetically pleasing.

“When we say complete street, we don’t mean just an improvement for motorists,” Boulder City Engineer Jim Keane said. “We are going to make improvements for everyone using the roads and sidewalks.”

The public works department plans to use $8 million in funding from the Regional Transportation Commission of Southern Nevada to widen the sidewalks, add bike lanes and create new medians.

Public Works Director Scott Hansen said the project is expected to begin in 2018, when the Interstate 11 bypass is scheduled for completion.

“We hope to have the RTC funds locked in for 2018, and we expect to start then,” Hansen said. “This project is a way for us to counter the effects of the bypass by making our streets more accessible to residents and tourists.”

The project is to cost $2 million out of the city’s general fund, which would be more expensive than the $1.4 million approved in 2011 to renovate the downtown area. That project included major utility upgrades, landscaping and paving, along with a decorative entry arch over Nevada Way.

“We are expecting the project to cost more than the downtown renovations because the highway is longer than downtown,” Hansen said.

Residents at the workshop seemed most concerned with access to businesses along the highway, with many of them worried that the proposed new medians would make it more difficult.

Don Rodriguez, owner of BC Pool Supply at 1643 Nevada Highway, said an overabundance of medians would make it harder for customers to get to his business.

“I don’t feel like my business is going to benefit at all from these upgrades,” Rodriguez said. “I think medians are just going to cut off access to my store.”

Rodriguez said he was worried that the current layout would not include turn lanes into his business, forcing customers to make U-turns.

Boulder City Chamber of Commerce CEO Jill Rowland-Lagan asked if the money to build medians could be used for other purposes.

“Do we have to have medians?” Rowland-Lagan asked. “It just seems like we could use that money for something else.”

The city is not required to use RTC money for building medians if residents do not want them, according to Hansen.

“We are thrilled that everyone is giving such good ideas, but RTC money does have to be used for road improvements,” he said.

Resident Dale Napier expressed concern about crosswalks on the roadway, which he said were too hard to see even for longtime residents.

“I use these roads as a motorist, cyclist and pedestrian,” Napier said. “I have been using these streets for years, and I even forget about the crosswalks on the highway. That must be fixed because the lack of visibility is a safety hazard.”

Keane said the city has every intention of creating safer streets for everyone.

“We have heard the concerns about the crosswalks, and that is a priority for us,” Keane said. “We are considering using LED lights like they use on the Strip. I was downtown the other day, and I could see those lights from way down the road.”

The public works department is looking to set up one-on-one meetings with business owners on the highway. Those who want to set up an appointment can call 702-293-9200.

Contact reporter Max Lancaster at mlancaster @bouldercityreview.com or at 702-586-9401. Follow him on Twitter @MLancasterBCR.

MOST READ
THE LATEST
Toll Brothers gets split decision

The development of the area near Boulder Creek Golf Course known as Tract 350 (the sale of which is slated to pay for the majority of the planned replacement for the aging municipal pool) may have hit a snag last week as the planning commission voted 5-1 to deny the developers’ request to build houses closer to the street than is allowed under current law.

Council gives nod to 185 new hangars

There is at least one part of Boulder City that is set to see growth in the coming years. A lot of growth.

Boulder City ready to celebrate America

Boulder City resident James Cracolici may have put it best when he called the annual July 4 Damboree, “The crown jewel of all events held in Boulder City.”

BC can ban backyard breeders

Although there is nothing on any city agenda yet, the resolution of the issue of whether pet breeding will be allowed in Boulder City took a huge step forward last week as Nevada Attorney General Aaron Ford released an official opinion on the intent and limitations of state law that had been requested by city staff last year.

Completion dates for two road projects pushed back

Mayor Joe Hardy tacitly acknowledged that Boulder City gets, perhaps, more than its fair share of funding from the Regional Transportation Commission, given the city’s size.

Businesses recognized at Chamber awards night

The Boulder City Chamber of Commerce’s annual installation and awards night featured many business owners in town and even had an appearance, albeit an A.I.-generated one, by Audrey Hepburn.

Parallel parking approved

Like so many other things in the world of Boulder City government, the issue of reconfiguring parking in the historic downtown area along Nevada Way, which generated enough heat to cause council members to delay a decision up until the last possible moment, ended with more of a whimper than a bang.

Ways to reduce summer power bills

Now that the thermometer is on the rise outdoors, the cost to cool homes and businesses on the inside is doing the same.