Boulder City’s Public Works Department is in arbitration with one of the lead contractors of the Nevada Way reconstruction project after the company claimed the city paid it $200,000 less than it was owed.

Wells Cargo, the company that repaved Nevada Way during the project, said it was supposed to receive $3 million for its work, according to Public Works Director Scott Hansen. The city only paid it $2.8 million.

Hansen said Wells Cargo failed to complete the project on time, which, as part of the agreement, allowed the city to deduct money from the total. The four-month project was supposed to be completed by August 2012, but Wells Cargo didn’t finish it until February 2013.

“They were supposed to pay (the city) $1,500 per day they were late,” Hansen said. “We followed the letter of the contract.”

Hansen said the late completion of the repaving did not sit well with business owners along Nevada Way. His office received several complaints about the extensive delay and jammed construction zones that hurt the businesses.

According to city records, Wells Cargo claimed that Southwest Gas hampered it from completing the project on time, but the city disagreed, citing that the amount of land Southwest Gas worked on during the project was not enough to slow down Wells Cargo’s job.

The city also claimed that Wells Cargo failed to complete the new street lights on time. Meetings between Wells Cargo and city employees were held with the intention of avoiding arbitration, but Wells Cargo refused to resolve the problem without going to arbitration, according to city documents.

Now, both sides will do battle as they go through depositions and formal testimonies, which could take months, according to Hansen.

“Unfortunately these can be long, drawn-out battles,” he said. “We just want the item to be resolved as quickly and economically as possible of course. I want to spend the taxpayer dollars building products and projects for the people.”

Mike Arriola, division manager for Wells Cargo, said the company could not comment on the matter because of pending litigation.

THE LATEST
Tract 350 sale approved

Whether it will be enough to fund the projected $40 million-plus pool complex the city would like to build is still — given the realities of the current inflationary economic environment — an open question.

Search for new city manager underway

Give him some credit. Recently-departed city manager Taylour Tedder may have left with just a few weeks of notice, but he did try to begin a process for finding his replacement as one of his final acts.

Tedder looks back on tenure

Despite being in Boulder City less than three years, Taylour Tedder said he will always have a place in his heart for the town he served as city manager.

Mays in as interim city manager

May 8. That is City Manager Taylour Tedder’s last day working for Boulder City. In other words, Tuesday was Tedder’s final city council meeting.

Council head fakes on pet breeding vote

It may seem to some as ironic that, at the same meeting where the lead animal control officer for the city spoke passionately about animals being abandoned by their owners in the desert around Boulder City and in which the council made clear that they expect city staff to return with a proposal for mandating microchipping of pets, that the city council considered a bill to amend city code to allow for pet breeding and fostering of up to eight dogs on a property within city limits.

Council mulls 2025 fiscal year budget

At a special meeting of the City Council on March 31,ith councilmember Matt Fox absent, the other four members of the council heard an overview of expected revenue and expenses for the 2025 fiscal year, which starts on July 1.

To chip or not to chip?

In its second time at the plate, as it were, the proposal by Boulder City Councilmember Cokie Booth to require that pets within BC be microchipped ended up with a lot of people talking about maybe taking a swing at the ball but no one actually doing so.

Council candidate slate set

A total of seven candidates for city council and three candidates for justice of the peace of Boulder Township will face off in the primary election scheduled for June 11.