Buchanan project will alleviate flooding

Boulder City is about to break ground on one of its largest flood control projects in recent years to help alleviate excess water along Buchanan Boulevard.

The project, which will cost $4 million, is expected to begin within the first two weeks of September, according to Public Works Director Scott Hansen. Funding for the project comes from the Regional Flood Control District.

The project will be the second largest of its kind since the district began working with Boulder City, according to district spokesperson Kelsey Hand. The largest was the $4.6 million Hemenway Channel in 1990.

Planning for the Buchanan project began in 2010, but was put on hold because construction was about to begin for the Nevada Way project, Hand said. That project included major utility upgrades, landscaping and paving, and the entry arch over Nevada Way.

Preparation for the Buchanan project resumed last year.

“What we don’t know yet, is when exactly it’s going to start,” Hansen said.

The city is scheduled to meet with Meadow Valley Contractors soon to discuss construction, including how Buchanan will be broken down during each phase, Hansen said. The Phoenix-based company specializes in heavy highway and civil construction projects.

The project will mainly consist of an underground pipe that will transfer water on Buchanan from Elm Street to El Camino Way. Upgrades to the concrete channel along Buchanan will be included.

“When we get a good rainstorm, it bubbles right back over the road on Buchanan,” Hansen said. “One of the biggest benefits will be keeping the water below ground in the storm drain where the water will dump into the channel near the hospital.”

Northbound Buchanan will have one lane closed during the span of the nine-month project, but Hansen said the construction shouldn’t be too much of a hindrance for locals.

“Our residents are really smart. They know how to get around the construction,” he said. “And for the most part, Buchanan has more capacity than it really needs on a daily basis.”

Hansen said residents on El Camino will be affected the most by the construction at first, but said that the upgrades would take place only during daytime hours.

“I’m sure when construction starts we’re going to have some complaints, but that’s just part of the nature of the business,” he said.

The four-phase project is expected to be completed by June.

Contact reporter Steven Slivka at sslivka@bouldercityreview.com or at 702-586-9401. Follow @StevenSlivka on Twitter.

MOST READ
LISTEN TO THE TOP FIVE HERE
THE LATEST
Really better buy that helmet

With a couple of significant amendments, the city council voted unanimously to pass an ordinance regulating the use of e-bikes and e-scooters in Boulder City. The ordinance passed unanimously Tuesday and will take effect on Sept. 18.

Nevada Way to go Pink … and pay for the privilege

The main topic of discussion was color. As in color of a building when the board of the Boulder City Redevelopment Agency (aka the city council) met two weeks ago.

City to nix admin services dept. in favor of deputy city manager

In a move that is really little more than “cleanup” (i.e., bringing official city code into sync with decisions made by the city council more than a year ago), the council voted to approve changes to city code related to the created-but-not-yet-filled position of deputy city manager.

Better buy a helmet …

It was just the opening salvo, but it appears that lost patience with riders of e-bikes and scooters are to the point that they are ready to go well beyond the “Well, how about more education” approach they opted for back in April.

Boulder City approves fire captains’ 2-year contract

For those who may have seen any of the recent social media posts put out by reps of the firefighters union calling out the city about pay and benefits, they might have been surprised that one collective bargaining agreement covering fire department personnel was approved by the city council this week without any discussion at all.

What’s on the pole?

There are 1,450 power poles in Boulder City and 880 of them support equipment owned by private companies who don’t pay for the privilege.

Shooting gets another look

It’s a case that captured the attention of many in Boulder City more than four years ago and has kept that attention ever since.

Advocate for preservation?

It is not often in Boulder City that there is resident pressure for the city to create a new position and hire someone to fill it. But that is the situation discussed recently by the Historic Preservation Commission.