New $21 million pool facility proposed

City Council supports building a new pool rather than renovating the current one after hearing the recommendation of an ad hoc committee and seeing results of a recent study.

At their Tuesday, April 13, meeting, council members agreed that the best option for the community is to build a new pool rather than renovate the one at Broadbent Park due to its deteriorating condition.

“Our goal was to take advantage of as much of the existing as possible … this will allow you to see what you can do and what the cost would be,” said SCA Design Architect Sheldon Colen.

SCA Design was hired to conduct a study for the city’s ad hoc pool committee on the cost of renovating or replacing the pool.

The company estimated it will cost approximately $21 million to build a new pool facility that would have an 8,600-square-foot, 35-meter-by 25-yard competition pool, a 2,250-square-foot recreation pool and an approximately 40,000-square-foot building.

Councilman James Howard Adams, who was vice chair of the ad hoc pool committee, said even though these plans were conceptual he was pleased with them.

“Some of these things might change and vary, but I think this shows that this is absolutely doable. … After all the discussions that we had on the committee with looking at rehabilitation, looking at a new facility, we really did try to find the middle ground,” he said. “I think that this right here looks to be … the best use of the people’s money.”

Optional features

Colen said they also made a list of items that could be added or removed and what the cost or savings would be. They are:

Adding a 1,900-square-foot splash pad and putting new equipment on the existing 900-square-foot kids’ pool, $913,247 cost; putting in a smaller pool that is 6,250-square-feet, 25-meter-by-25 yard pool, $610,859 savings; adding solar panels and equipment, $546,662 cost; and converting the existing locker rooms into office space, $275,503 cost.

Councilwoman Tracy Folda asked what the life expectancy of the proposed pool would be.

Colen said they estimated it would have 30 years of usability. He also said the goal was to not have to replace it after that. Rather, it would just need to be upgraded.

Councilwoman Claudia Bridges said she was glad the project did not lose the vision of being a community pool.

Councilwoman Judy Hoskins asked how inflation and the length of time to complete the project would affect the $21 million estimate.

Colen said they can’t control inflation, but it has been taken into account.

“The longer it takes, the price may raise up a little bit, but our goal would be to not take that as ‘let’s just build it and spend your money,’” he said. “Our goal would be to say this is what we want, how can we save you even more money.”

To repair, renovate and bring the current pool up to code, SCA Design estimated it would cost almost $7 million. That amount was based on visual findings and did not include any past or current pool leaks. It also did not include any potential problems that could arise when renovating older facilities. Additionally, even if the pool is renovated it will still be too shallow to hold swim meets there.

The next step for this project is the two questions on the June 15 ballot about funding.

To help inform voters before they have to weigh in on the ballot questions, council directed staff to be available to provide information about the pool and study and for parks and recreation staff members to provide tours of the facility upon request.

“The community really, I think, needs to understand the conditions that are there now,” said Mayor Kiernan McManus. “If they’re not addressed very quickly, we will just be closing the facility.”

The city has created a website about the project with all of the supporting information and the proposed plans. It is available at www.bcnv.org/pool.

Additional gardens

Council also approved budgeting $75,000 in the five-year capital improvement plan for a second community garden, which will likely be built at ABC Park, 801 Adams Blvd.

Public Works Director Keegan Littrell said the city had received a bid of approximately $100,000 to install one with 25 individual garden plots.

McManus said he brought the item forward because he had heard from people that they had been waiting for years for a spot, but he did not expect it to cost that much.

“To be completely honest, I was shocked by the $100,000 also,” added Littrell.

The city is also eliciting help and input from “interested parties” in the community about what they could contribute to the project.

Contact reporter Celia Shortt Goodyear at cgoodyear@bouldercityreview.com or at 702-586-9401. Follow her on Twitter @csgoodyear.

MOST READ
LISTEN TO THE TOP FIVE HERE
THE LATEST
Ruth, Burrows make state podium

Competing at the 3A state meet, Boulder City High School wrestlers Otis Ruth and Coen Burrows made their way onto the podium at the Winnemucca Events Center on Feb. 14.

Lady Eagles advance to state tourney

Boulder City High School girls basketball will be making their first 3A state tournament appearance since 2019.

Just play by the rules during the parade

If you’re reading this and have not yet read the page 1 article about the concerns of the Damboree committee and the popular water zone, I will stop typing until you do.

Protecting student programs at King

Editor’s Note: After the printing of this edition, Martha P. King Elementary received word from the school district that it won its budget appeal and that both the PE and music positions will not have to go part-time this fall.

Cox awards $250K for railroad trail

It’s one of the most popular trails within the Lake Mead National Recreation Area, and thanks to a generous grant, will soon be receiving a makeover.

Damboree water zone may dry up

The July 4 Damboree is not only one of the most popular parades in the state, it is a big part of Boulder City’s history.

Dynamic duo lead Eagles basketball into playoffs

Ending the regular season on a high note with a 17-10 record, Boulder City High School boys basketball won their final two regular-season games.

Lady Eagles to host playoff game

Finishing the regular season on a high note, Boulder City High School girls basketball won their last two regular-season games, earning the right to host a home playoff game.