As Railroad Pass travel center nears completion, plans for second hotel tower underway

Construction of the new $10 million travel center at Railroad Pass is progressing and is expected to be completed in time to open at the start of the new year.

Joe DeSimone, owner of the casino-hotel northwest of Boulder City, said tanks are in the ground, the canopies are up and the convenience store is halfway done.

“We’re moving as fast as the highway will allow us,” DeSimone said. “As long as (the Nevada Department of Transportation) remains on schedule, we will open by Jan. 1.”

Work is progressing rapidly, though not as fast as it could. Completion of the center, being built on 16 acres south of the casino, has been delayed about three months. When construction began in late January, DeSimone expected it to be complete and open by September.

Despite the delays, DeSimone said NDOT officials have been extremely helpful and kept him notified of any changes or issues.

They also made accommodations for the casino’s customers from Boulder City, creating an access road that allows them to turn left from the property for an easier return home, DeSimone said, adding that was essential for them.

“People from Boulder City are our lifeline. There are more people coming home to Boulder City than to here from Henderson,” he said.

Another challenge is the lack of maps of the site, he said. They have encountered a few things that have slightly delayed construction, including a major connector for Cox Communications that provides internet service to the Boulder City area.

Second tower

As work on the center continues, DeSimone is already making plans to expand the hotel. He is working with an architect and the city of Henderson to build a second tower featuring 220 rooms.

“We are in the planning stages,” he said.

The tower will be east of the existing tower across from the small parking area and will connect via a bridge over the main entrance.

DeSimone said that once the travel center opens, he should be able to determine the need for the additional hotel rooms fairly quickly.

“With the studies we have done, we are anticipating success right away,” he added. Currently, roughly 75 to 100 people are working on the construction of the travel center and truck stop, DeSimone said.

DeSimone said he expects to hire about 15 to 20 people for the travel center and expects to start staffing the facility in the coming days.

“I would love to hire local people,” he said.

Two fueling areas

The new facility will include a Chevron gas station with 20 pumps, a nonbranded fueling center for trucks with seven pumps, propane sales, a clean-out station for recreational vehicles and a truck scale.

There also will be six charging stations from Tesla, with the capacity for more, as well as charging stations for other vehicles.

DeSimone said he is especially pleased about the partnership with Tesla because it means the charging stations will show up on the auto manufacturer’s national map.

The travel center itself will measure 8,500 square feet and include showers and a lounge for truckers, an expanded convenience store, a Capriotti’s Sandwich Shop, “clean, nice bathrooms” and 15 slot machines, as long as they received approval from the Nevada Gaming Commission in November.

“We used a lot of observation and talked to truckers who stop here regularly,” said Joe Wilcock, the property’s new general manager, of how the leadership determined the best features for the truck stop.

There are also plans for an as-of-now-unnamed fast food restaurant.

Wilcock said addition of the truck stop and travel center makes the property distinctive.

“There are not many casino/truck stop combinations in the country,” he said.

Separate identities

Though they will be located on the same property and have the same owner, the two entities will have their own identities, including separate websites, Wilcock said.

However, there will be some connections.

Wilcock said owning the truck stop and travel center will allow for some special promotions for their casino regulars, such as “free gas at the Pass.”

Once the Nevada Department of Transportation is finished with its portion of Interstate 11, the land it is currently using for U.S. Highway 93/95 will be returned to the casino.

Tony Illia, spokesman for NDOT, said he was told by the project manager early Wednesday morning that the road in front of Railroad Pass will be vacated by Jan. 1, with completion of the first phase of I-11 on track for the end of December or early January at the latest.

DeSimone estimates it will take four or five weeks to transform the former highway into a parking lot. Preliminary work has already been done, and there are big piles of fill in place to level the surface, he said.

There will be parking for about 100 trucks and 30 recreational vehicles in addition to an expanded parking lot for cars.

Also included in the project is a separate parking area and access to the River Mountains Loop Trail.

Hali Bernstein Saylor is editor of the Boulder City Review. She can be reached at hsaylor@bouldercityreview.com or at 702-586-9523. Follow @HalisComment on Twitter.

THE LATEST
BCHS students win robotics competition

A trip to the workshop for the High Scalers, the robotics team at Boulder City High School in 2024 was much like a visit in 2023. Stuff used to make and practice with the robots built by the team everywhere, six or seven kids gathered there after school and a faculty advisor ensconced in the back of the room at a desk.

Mays in as interim city manager

May 8. That is City Manager Taylour Tedder’s last day working for Boulder City. In other words, Tuesday was Tedder’s final city council meeting.

Council establishes separate pool fund

Things appear to be heating up in terms of motion toward at least initial steps in Boulder City building a new pool. Those steps are not anything that residents will see for a while, but they set the stage.

BCPD closes graffiti case

Thanks to business surveillance cameras, the city’s vigilant license plate reader and “good old-fashioned detective work,” one of the most visible crimes the city has seen this year was solved and arrests made.

Ethics article on hold

In last week’s article on former Boulder City Fire Chief Will Gray’s termination, it mentioned that a follow-up on the Nevada Ethics Commission complaint filed by Gray against Councilman Steve Walton would appear in this week’s edition.

Student Council shines with 2 awards

The Boulder City High School Student Council received a pair of prestigious awards within the past two weeks to add to the list already on their proverbial mantle.

Former fire chief Gray discusses termination

The past few weeks have been a whirlwind for the city, and specifically the fire department, as questions of whether or not Will Gray was still employed as that department’s chief spread through town.

Breeding proposal breeds opposition

Judging by the number of people speaking out against it during public comment at the last city council meeting and the tone of numerous social media posts, the proposal to allow for licensed pet breeders to operate in Boulder City is itself breeding a growing opposition. And the opposition appears to be spilling over into other pet-centric issues, including the fact that, unlike anywhere else in Clark County, Boulder City does not require dogs to be on a leash in public.

Wanted: A good home for theater seats

For those who have either grown up in Boulder City or are longtime residents, the Boulder City Theatre holds a special place in the hearts of many.

Hangars and OHVs and pool people, oh my

In a meeting with only two council members present in the room (and the other three on the phone) and in which the major attention was divided between a contentious possible law concerning pets and the fact that the city manager had announced he was leaving for a new job on the East Coast, the council did take a series of other notable actions.