Backup to aging electrical transformer arrives

Boulder City’s power supply is getting a new backup transformer that will increase the system’s reliability.

“The existing BC Tap transformer doesn’t have the capacity to deliver the large amount of energy needed during summer,” said Rory Dwyer, the city’s electric utility administrator. “Also, the existing transformer’s age (54 years) makes it more likely to fail during hot weather, when people would be most impacted by a power outage. The new transformer is sized to provide year-round backup capacity.”

The transformer costs approximately $1.1 million and weighs about 109 tons. It was installed on the concrete pad at the Boulder City Tap off Utah Street on Thursday, April 5. The installation took eight hours, according to Dwyer.

“Transformer replacement every 50 years is a prudent planning target,” Dwyer said. “The BC Tap is the city’s only transmission substation transformer. Therefore, city staff doesn’t expect a transformer replacement of similar scale in the foreseeable future. Two of the city’s 12 distribution substation transformers are planned to be replaced after July 2020, but these transformers are only one-tenth of the size of BC Tap.”

The new transformer will be operational in November.

“Replacing the circuit breakers will require a longer outage at BC Tap than was needed to set the transformer,” Dwyer said. “Residents will not notice an outage at BC Tap, except if a problem were to occur on the city’s normal transmission feed at the same time. That is not likely to happen, but if it did, better that it be in cool weather. Thus, the delay until November.”

As part of ongoing efforts to upgrade the city’s aging electrical system, Substations No. 3 and No. 4 will be replaced in fiscal 2020-2022, according to Public Works Director Scott Hansen. That project will cost approximately $6.5 million.

Before they can be replaced, however, the electric feeders for them need to be upgraded. Hansen said that design will begin on the Avenue G feeder and the golf course feeder in July.

Contact reporter Celia Shortt Goodyear at cgoodyear@bouldercityreview.com or at 702-586-9401. Follow her on Twitter @csgoodyear.

MOST READ
LISTEN TO THE TOP FIVE HERE
THE LATEST
Cross county runners look to improve this season

Bringing back a handful of runners who made the 3A state meet a season ago, there’s an optimistic outlook for Boulder City High School cross country this upcoming season.

September offers something for everyone at Boulder City Library

As the heat finally comes down outside, inside the library we have cooked up some amazing events for this upcoming September that we’re excited to tell you all about. No matter what age our patrons are, we pride ourselves on having something for everyone, and our programming schedule for September is no exception.

City grants CUP to Methodist Church

The Boulder City United Methodist Church cleared a major hurdle last week in its desire to build a church of its own; something it’s wished to do for two decades.

Schools welcome new faces on campus

In the blink of an eye, summer vacation for students and faculty from Boulder City’s five public schools was over and school was back in session.

Art in the Park warns of scam

Art in the Park is arguably Boulder City’s biggest event of the year. And with any event of its size comes an opportunity for unscrupulous behavior.

Stankovic scores five goals in victory

Boulder City High School girls soccer advanced to 2-0 on the season, defeating rival Virgin Valley 5-3 on Aug. 19.

Lady Eagles tested early on the court

Boulder City High School girls volleyball advanced to 5-5 on the season, after splitting a pair of games last week.

Looking back on Sept. 11

In just over two weeks, the nation will honor the 25th anniversary of one of the worst days in the history of this country.

Titus, mayor tout project

Saying that “businesses are the lifeblood of our community,” Mayor Joe Hardy helped lead a brief press conference Friday to discuss work to be done as part of Phase II of the Nevada Way Reconstruction Project.