Ready (almost) to roll: Construction of I-11 to be finished by end of year

For nearly three years, large pieces of construction equipment have dotted the landscape around Boulder City as work has progressed on the building of Interstate 11.

With the arrival of 2018, crews are on pace to have the project completed before the end of the year.

The Nevada Department of Transportation and the Regional Transportation Commission of Southern Nevada have been working simultaneously to build the first two phases of the interstate highway, which will eventually connect Las Vegas to Phoenix.

NDOT’s 2.5-mile section, which covers the area from Railroad Pass to U.S. Highway 95, is set for “contractual completion” in April, according to project manager Ryan Wheeler, and traffic is expected to be moved to new alignments before that.

“Overall, given the circumstances, it has gone as smoothly as possible,” Wheeler said. “We are excited to get it open to the motorists.”

Monika Bertaki, spokesperson for the RTC, said it is scheduled to complete its 12.5-mile stretch from the intersection with U.S. 95 to U.S. Highway 93 near the Hoover Dam Bypass Bridge in October, when it will open to traffic.

According to Wheeler, the contractual completion date — when all details have been finalized and signed off on — has been moved to April, but he expects the majority of the work to be finished by mid-February.

That will allow the agencies to shift traffic from northbound U.S. 93 onto the interstate heading toward Henderson, as well as opening the new Railroad Pass interchange, Wheeler said.

“The new 95-I-11 interchange will be open before May,” he said. “Once Phase 1 is complete, if you want to go onto southbound 95, you won’t have to divert. You can take I-11.”

Plans have been adjusted continually throughout the project to accommodate issues that have caused delays.

Joe DeSimone, owner of the Railroad Pass Casino, had expected the land in front of the casino that is now being used for a portion of U.S. 93/95 to be returned to him before the end of 2017.

Though Wheeler commended Fisher Sand and Gravel for its work, any construction project will inevitably run across challenges that delay completion. One of the biggest challenges was relocating utilities, he said.

Bertaki said the RTC and its primary contractor, Las Vegas Paving, haven’t encountered any issues that have caused delays.

Before Phase 2 opens, “the contractor will go through punch-list items for quality assurance and then review or modify any items prior to completion,” she said.

Ground was broken for the four-lane interstate in April 2015 during a ceremony attended by numerous local, state and national officials. The highway will include interchanges at U.S. Highways 95 and 93, 10 bridges, four wildlife undercrossings, one wildlife overcrossing, an off-highway vehicle crossing and a scenic parking area overlooking Lake Mead.

Overall, the project will cost $318 million, with $249.2 million coming from federal funds.

Wheeler said an official opening ceremony will likely be held in October when both phases are complete.

The project has created hundreds of jobs.

Tony Illia, public information officer for NDOT, said there are currently 60 workers on-site, but there have been as many as 200 during the peak of construction activity.

Bertaki said there are currently 90 construction employees working on Phase 2.

“The number of employees can vary day by day due to the different aspects of the project. Thus far, there have been 1,078 construction employees on the project.”

Hali Bernstein Saylor is editor of the Boulder City Review. She can be reached at hsaylor@bouldercityreview.com or at 702-586-9523. Follow @HalisComment on Twitter.

THE LATEST
Former fire chief Gray discusses termination

The past few weeks have been a whirlwind for the city, and specifically the fire department, as questions of whether or not Will Gray was still employed as that department’s chief spread through town.

Breeding proposal breeds opposition

Judging by the number of people speaking out against it during public comment at the last city council meeting and the tone of numerous social media posts, the proposal to allow for licensed pet breeders to operate in Boulder City is itself breeding a growing opposition. And the opposition appears to be spilling over into other pet-centric issues, including the fact that, unlike anywhere else in Clark County, Boulder City does not require dogs to be on a leash in public.

Wanted: A good home for theater seats

For those who have either grown up in Boulder City or are longtime residents, the Boulder City Theatre holds a special place in the hearts of many.

Hangars and OHVs and pool people, oh my

In a meeting with only two council members present in the room (and the other three on the phone) and in which the major attention was divided between a contentious possible law concerning pets and the fact that the city manager had announced he was leaving for a new job on the East Coast, the council did take a series of other notable actions.

Look, up in the sky…

Ron Eland/Boulder City Review

Council hears plan for golf course turf reduction

Reducing water usage in Southern Nevada has been a subject that has affected the look of clean, green Boulder City multiple times in the past year.

City confirms fire chief no longer employed

After more than two weeks of inquiries by the Boulder City Review, late Tuesday afternoon the city confirmed that Boulder City Fire Chief Will Gray is no longer employed.

Residents weigh in on 99 Cents Store’s shuttering

In what came as a surprise to many who are frequent shoppers, officials from 99 Cents Only Stores announced last week that all of their 371 locations will be closing over the next several weeks.

Four suspects arrested in graffiti case

On Jan. 22, many residents were shocked by a rash of graffiti throughout town, which included the historic Boulder City Theatre.